Project Portfolio and PMO | Part 6 of 8

Dependencies and Conflicts Between Projects

Five kinds of dependency between projects, a simple list that makes them visible, and a rule that decides conflicts over people, assets and shutdown windows.

In the register every project has its own row and looks independent. On the shop floor the projects meet: at the same machine, in the same shutdown week, at the desk of the same person. Most delays that a project manager cannot explain from the own plan come from another project.

Five kinds of dependency

Kind What it is How to handle it
Result One project needs what another delivers The milestone of the giver is a start condition of the taker
Key person Two projects need the same single expert Named in the capacity sheet, second person trained
Asset Two projects change the same line, machine or system The owner of the asset decides the order
Time window Two projects need the same shutdown or ramp-up phase One shutdown calendar for the site
Data and system Two projects change the same master data or interface One release plan for the system

One list, kept by one person

The register owner keeps a list with one row per dependency: the project, what it depends on, the kind, what is needed and by when, the state and an owner. Three states are enough: on track, solved by sequence, open conflict.

The example plant found seven dependencies among its 18 active and queued projects. Some of them:

  • The MES pilot builds its interfaces on the new ERP release. It starts in September, after the ERP upgrade ends in May. Solved by sequence.
  • The automated test cell reuses the safety concept of the test bench retrofit and needs it by July. On track.
  • The test cell and the layout change in hall 3 both want the August shutdown and the same maintenance crew. Open conflict.
  • Three projects need the one controls engineer who knows the safety controls of the test benches. Open conflict.

Notice how many dependencies disappear through the order of the projects alone. A portfolio that starts fewer projects at once has fewer conflicts to manage. This is one more reason for the queue.

The shutdown calendar

Most plants have two or three windows per year in which lines stand, and every project that touches a running line wants them. The calendar lists each window, the area or asset, the projects that ask for it and the decided order.

How conflicts are decided

  1. The two project managers try to solve the conflict and bring one proposal to the board.
  2. If they cannot agree, the rank decides. The higher ranked project gets the person, the asset or the window.
  3. The board confirms and moves the planned dates of the lower project. The delay is visible in its report, with the reason.

In the example, the layout change in hall 3 has rank 6 and the test cell rank 8. The layout change keeps the August shutdown. The installation of the test cell moves to two weekends in September. That costs EUR 9,000 in overtime and saves three months of waiting for the next window.

What the board wants to see

Not the whole list. The board sees three numbers each month: dependencies listed, open conflicts, and items needed within the next 60 days that are not yet solved. In December 2026 that was seven, two and none. An open conflict stays on the agenda until it has a decision, an owner and a date.

Dependencies are not a sign of poor planning. They are what happens when a plant changes several things at once. They become a problem only when nobody has written them down.