Project Portfolio and PMO | Part 3 of 8

Capacity Against Demand: How Many Projects Fit

Name the bottleneck resources, count their capacity in person-days per month, compare it with the demand of all projects and start only what fits.

Money is rarely what limits the projects of a plant. The limit is a handful of people whom every project needs: the process engineers, the controls technicians, the ERP key users. As long as their time is not counted, every new project looks possible.

Why fewer projects finish faster

One team has 30 person-days per month for projects. Three projects need 60 person-days each and bring EUR 120,000 per year each. Run all three at once, and each gets 10 person-days per month: all three finish after six months. Run them one after another, and they finish after two, four and six months. The average lead time falls from six to four months, and by the end of month six the first two projects have already earned EUR 60,000. The same people, the same work, no overtime.

Count the capacity

Ask the project managers whom they wait for most often. The same names come up. The example plant found five functions with 17 people. Each person is present 18 days per month on average, after vacation, sickness and training. Half of that time belongs to daily business, half to projects. Process engineering: 5 engineers x 18 days x 50 percent = 45 person-days per month.

Each project states its remaining person-days per bottleneck resource and its remaining months. Demand per month is one divided by the other. The line 2 project needs 70 person-days of process engineering in five months: 14 per month.

Bottleneck resource Capacity All 22 projects Load
Process engineering 45 113 251 %
Automation and controls 27 51 189 %
ERP and IT key users 18 32 178 %
Quality engineering 27 43 159 %
Maintenance project crew 36 69 192 %
Total 153 308 201 %

Capacity and demand in person-days per month.

The plant had promised twice the work its key people can do. So every project took twice as long: the five projects finished in the year before needed 14 months on average instead of the planned 7. Overload of this kind does not show as overtime. It shows as waiting.

The start rule

  1. Walk down the ranking from the top, must projects first.
  2. A project starts when every bottleneck resource it needs stays at or below 90 percent of its capacity.
  3. If it does not fit, it waits in the queue and keeps its rank.
  4. A lower project may pass a higher one only when it fits into the gap and does not move the planned start of the higher one.
  5. When a project ends, the walk is repeated for the freed capacity.

What the walk produced

The three must projects start. So do the line 2 project and the changeover project, which bring process engineering to 31 of 45 person-days. The scrap project fits. The test cell and the kanban project do not: they would lift process engineering to 44 and 46 person-days. Further down, the heat recovery project starts because it needs mainly the maintenance crew.

The result: 8 projects active, 10 in a ranked queue, 4 stopped. Demand falls from 308 to 112 person-days per month, 73 percent of the capacity. The highest load of one resource is 89 percent instead of 251.

The queue is a promise

Every queued project gets a planned start month and the name of what has to end first. The test cell starts in April, when two projects end in March. The MES pilot starts in September. In the plan for twelve months no resource rises above 90 percent, and twelve projects finish.

A sponsor who hears “your project starts in May, after line 2 is done” can live with that. It is easier to accept than a project that starts at once and then stands still.