A register in which every project has priority one is still only a list. The ranking turns it into an order. It does not replace the decision of the management team. It makes the discussion short.
Benefit as a number with a baseline
A benefit that is not written as a number cannot be ranked, and it cannot be checked later. Each project states a measure, its baseline, the target and the amount in EUR per year at full effect. Three examples from the plant:
- Assembly line 2 rebalanced to takt (P-04): 12 instead of 14 operators per shift on two shifts. Four hirings on another line are avoided, overtime is halved. EUR 310,000 per year.
- Changeover reduction on the machining centers (P-06): 1,200 machine hours freed replace external machining at EUR 150 per hour. EUR 180,000 per year.
- Scrap reduction in casting machining (P-07): scrap cost falls from EUR 550,000 to EUR 330,000. EUR 220,000 per year.
Two rules keep the numbers honest. The line manager who will carry the benefit in the budget signs the statement, not the project manager. And controlling checks the calculation. Must projects, driven by law, safety or a binding customer requirement, carry no amount, only the source of the obligation.
Five criteria, one scale
Every project gets 1 to 5 points on five criteria with fixed weights:
| Criterion | 1 point | 5 points | Weight |
|---|---|---|---|
| Benefit | Below EUR 25,000 per year | From EUR 250,000 per year | 30 |
| Strategic contribution | No link to a site objective | Without it an objective fails | 25 |
| Urgency | Can wait a year without loss | Window closes within three months | 15 |
| Risk | New technology, many unknowns | Done before, low uncertainty | 10 |
| Effort | Above 320 person-days | Up to 60 person-days | 20 |
Score = sum of weight x points, divided by 5. The maximum is 100. Risk and effort are scored in reverse: low risk and little effort give many points. Benefit and effort follow fixed steps, so nobody argues about a point.
P-04 gets 5 points for benefit, 4 for strategy, 4 for urgency, 4 for risk and 3 for its 180 person-days: (30 x 5 + 25 x 4 + 15 x 4 + 10 x 4 + 20 x 3) / 5 = 82. The MES pilot (P-08), strategic but large and uncertain, reaches 63.
The scoring round
Benefit and effort points come from the register. For strategy, urgency and risk, each member of the management team writes the points on a card, and all cards are shown at once. Only differences of two points or more are discussed, two minutes each, then the chair decides. For 22 projects this takes about three hours.
Three rules for the ranking
Must projects first. They are not ranked against the others, but they are counted in the capacity. In the example 3 of 22 are must projects, and they use 22 percent of the capacity of the key people. If everything is a must, nothing is.
A minimum score. Below 50 points a project does not start. In the example four projects fall below the line, with 46, 42, 41 and 41 points. Together they carry EUR 100,000 of the EUR 2,135,000 planned benefit, less than 5 percent, but they would have used 550 person-days.
No repairs afterward. The ranking is read out. Nobody changes a score later to move a project. If the board deviates from the ranking, it writes down why.
The ranking says what the site wants most. It does not yet say what the site can do. That depends on a handful of people.