A ranking and a capacity count are worth nothing if projects still start in the corridor. A site needs one place where a project starts or stops, and a few points on the way at which somebody asks whether it should go on.
The board is the management team with a different agenda
The portfolio board is not a new committee. In the example plant it is the plant manager as chair and the heads of production, quality, logistics, maintenance and controlling. One person, the register owner, prepares the meeting and keeps the log. The board meets on the first Tuesday of every month for 90 minutes.
| Item | Result | Minutes |
|---|---|---|
| Open decisions of the last meeting | Closed or new date | 10 |
| Portfolio overview | Green projects are not discussed | 15 |
| Red projects | Recover, change scope, hold or stop | 25 |
| Gates | Go, go with conditions, no | 25 |
| Capacity and next starts from the queue | Start months confirmed or moved | 10 |
| New proposals and open conflicts | Owner for the next step | 5 |
When the board stops a project
Starting is easy. The test of a board is whether it can stop. Four reasons are enough:
- The reason is gone: the customer, the product or the objective behind the project changed.
- The benefit shrank: the forecast is below 70 percent of the plan and no change of scope repairs it.
- It stays red: three reports in a row without a recovery plan the board believes.
- Something better needs the people: a higher ranked project waits for the same bottleneck resource.
Four gates
A gate is a decision point between two phases of a project, known from the stage-gate models of product development. For a plant a short form of our own is enough: four gates, five criteria each.
Gate 1, start. From idea to project. On the table: a one-page proposal, the benefit with its owner, score and rank, free bottleneck resources, a sponsor and a project manager.
Gate 2, plan. From planning to execution. A plan with milestones, a budget within 10 percent of the proposal, the benefit confirmed by controlling, the top risks with measures, people confirmed by their line managers.
Gate 3, go live. From execution to handover. The result is tested, users are trained, documents are updated, open points have owners, the line manager is ready to take over.
Gate 4, close. From handover to the benefit check. Handover signed, budget closed, the dates of the three benefit checks fixed, lessons recorded, people released.
Small projects, up to 100 person-days and EUR 50,000, pass only gates 1 and 4.
Three possible results
A gate review ends with go, go with conditions, or no. Conditions are limited to two, each with an owner and a date within four weeks. A no sends the project back one phase, into the queue, or ends it.
The line 2 project of the example came to gate 2 on 1 December 2026. The budget was EUR 60,000 against EUR 58,000 in the proposal. Controlling had confirmed EUR 310,000 of benefit per year, and three risks had measures. One criterion was open: of the people needed, 70 person-days of process engineering were confirmed, 20 of the maintenance crew were not. The result was a go with one condition, owned by the head of maintenance, due on 15 December.
The test of a gate
Count the results of the last year. If every review ended with a go, the gates are a ceremony and the real decisions are taken somewhere else.