The Project Register: Finding the Hidden Projects

What counts as a project and what stays line work, where hidden projects live, and how one register for the whole site is built in two weeks.

Ask a plant manager how many projects run at the site and you get a number. Ask the department heads one by one and you get a larger one. Look into the calendars of the key engineers and the number grows again. Nobody is hiding anything. There is simply no door a project has to pass before it starts.

A definition a department head can apply in one minute

Without a definition, everything is a project or nothing is. Both hide the load. The example plant, a maker of industrial pumps and valve assemblies with 380 employees, agreed on this one:

A project is a one-time undertaking with a defined result and an end date that needs more than 20 person-days or more than EUR 10,000, or that needs people from more than one department.

Everything else is line work and stays on the action list of its department. The thresholds are a choice. What matters is that they are written down and that one of them is about other departments, because those projects compete for the same people.

Where hidden projects live

The official list is rarely wrong. It is incomplete. Six places hold what is missing:

  • Department action lists with items that have been open for months and need other departments.
  • The investment plan and open purchase requisitions: every machine and every software package needs somebody to introduce it.
  • Commitments to customers and auditors with a date that nobody planned as a project.
  • IT and ERP request lists, which tie up key users in every department.
  • The calendars of key engineers, where recurring meetings carry project names that are on no list.
  • Improvement boards with initiatives that outgrew the team that started them.

The plant manager names the purpose of the search: to see the load, not to judge anybody. Every department head lists all undertakings that fit the definition, including the ones that are “almost done”. One person, the later register owner, checks the six sources, merges duplicates and gives each project one number, one name and one sponsor.

Result of the search Number
Undertakings found 26
On the official list before 11
Projects by the definition 22
Line work, returned to the departments 4

Half of the 22 projects ran without a start decision.

One row per project

The register is a table, not a tool. Each row holds the number and name, the objective in one sentence, the sponsor and the project manager, the class (must or choice), the benefit in EUR per year with the line manager who owns it, the budget, the effort in person-days, start, end and status.

Six statuses are enough: idea, queued, active, on hold, stopped, done. Only one of them allows a project to use people: active.

In the example, the 22 rows add up to EUR 2,135,000 of planned benefit per year, EUR 2,375,000 of budget and 3,510 person-days of effort. Three are must projects: a customer specification, a safety finding and an ERP release that loses vendor support.

The sentence that gives the register its power

A list that nobody has to respect is a report. The register becomes a steering instrument with one rule: line managers release their people only for projects with the status active. If a project is not in the register, it does not get people.

In practice the rule protects the departments, because it ends the quiet requests that fill the weeks of their best people. And once every project is visible in one place, the site can do what it could not do before: compare them.