Purchasing reports a million in savings. Controlling looks at the accounts and finds a third of it. The cause is almost never bad faith. It is the lack of rules that were agreed before the first measure was counted.
Rules first
Four rules, written with the controller, settle most arguments.
- Saving. Old price minus new price, times the actual quantity, for the same specification, for twelve months from the first delivery at the new price.
- Cost avoidance. The difference between a first offer or an announced increase and the agreed price. Reported separately and never added to savings.
- Market effects. Changes that follow an agreed index are neither a saving nor a loss of purchasing.
- Confirmation. Controlling confirms base, quantity and start month before a measure counts.
Four stages
A measure passes four stages: idea, evaluated, contracted, effective. Only the last one, with the first invoice at the new price booked, is a saving in the accounts. A report that mixes the stages promises money that has not arrived.
Two numbers per measure
Every measure has an annual effect and an effect in the fiscal year. The second depends on the start month. A measure that starts in month 4 counts nine months.
The pump plant of this series ran eleven measures in seven categories.
| Category | Annual effect (EUR) | Year one (EUR) |
|---|---|---|
| Machined parts | 204,000 | 144,000 |
| Castings | 115,200 | 57,600 |
| Freight | 100,800 | 75,600 |
| Sheet metal and welded parts | 96,000 | 56,000 |
| MRO and tools | 72,000 | 36,000 |
| Fasteners and standard parts | 72,000 | 48,000 |
| Electric motors | 50,400 | 42,000 |
| Packaging | 48,000 | 16,000 |
| Total | 758,400 | 475,200 |
EUR 758,400 is the run rate at the end of the year, 3.16 percent of the purchasing volume of EUR 24.0 million. EUR 475,200 is what the accounts of year one show, 1.98 percent. Both numbers are true. Report both, and say which is which.
Cost avoidance came on top and stayed separate: EUR 60,000 for energy bought at a fixed price in tranches, and EUR 48,000 for seals, where an announced increase of 4.0 percent was settled at 1.5 percent. Together EUR 108,000.
Key figures
Savings are one number of several. A few figures, reported every quarter, show whether purchasing steers the spend.
- Maverick share: from 11 to 4 percent.
- Contract coverage: from 55 to 72 percent.
- Active suppliers: from 340 to 165.
- Savings in the accounts and annual effect of all measures.
- Cost avoidance, reported separately.
- Orders per year: from 14,600 to 9,800.
The self-assessment with 25 statements rose from 21 to 72 points in the same twelve months.
Strategic and operational
None of this happens while five people spend 85 percent of their time on orders. The plant separated the roles.
- Category buyers. Two buyers with five categories each. Spend analysis, strategy, market, awards, contracts, savings.
- Operational buyers. Two buyers. Orders outside contracts, confirmations, expediting, invoice questions.
- Materials planners. Call-offs against frame contracts, without a buyer.
- Requesters. Demand, specification and budget. Members of the category team.
The time came from the Simplify field. A catalog supplier for MRO, one supplier with a bin system for fasteners and fewer carriers removed 4,800 orders per year. At 20 minutes per order that is about 1,600 hours, the time of one buyer.
Where it connects
Strategic procurement decides what is bought from whom on which terms. Keeping the chosen suppliers performing is supplier management. The stock parameters behind the call-offs belong to inventory management, and what is checked at the door to incoming inspection. Each has its own series.
The sequence of this series is short: see the spend, sort the categories, decide the levers, source on total cost, secure it in a contract, measure the effect. The first step needs two weeks and a spreadsheet.