Strategic Procurement | Part 5 of 8

Price and Cost Analysis: Cost Breakdown, Target Price and Price Formula

How to read a supplier price with a cost breakdown, set a target price and agree a price adjustment formula for material and energy.

Competition sets a fair price when several suppliers can quote. For a casting with one approved foundry, there is no competition to ask. Here facts replace it.

Four ways to judge a price

  • Price comparison. What do others quote for the same item?
  • Price history. How did the price move against the indexes for material and wages?
  • Cost breakdown. What does the supplier say the price consists of?
  • Own cost estimate. What should the part cost with good practice?

The pump plant of this series buys castings for EUR 5.76 million from 6 foundries, a category in the Partner field. The largest part is pump housing H-200 with 24,000 pieces per year at EUR 60.00.

The breakdown of H-200

The foundry filled in the price breakdown form. The plant built its own estimate beside it.

Element Quoted (EUR) Estimate (EUR)
Material, 20 kg melt weight 22.00 22.00
Energy 4.80 4.80
Labor 10.80 9.00
Machine and tooling 12.40 11.20
Scrap and rework 3.00 2.00
Overhead, administration and sales 4.20 3.90
Profit 2.80 2.80
Price per piece 60.00 55.70

The estimate uses 0.25 instead of 0.30 labor hours and a scrap rate of 4 instead of 6 percent. The gap is EUR 4.30, 7.2 percent of the price.

Three readings

Material and energy make EUR 26.80, 45 percent of the price. They follow the market. They belong in a formula, not in a negotiation.

Labor, machine and scrap make EUR 26.20. Here lies EUR 4.00 of the gap. This is the field for joint improvement: cycle time, yield, batch size.

Overhead and profit make EUR 7.00, 11.7 percent. That is a normal range. Attacking the margin of a partner you cannot replace is the wrong start.

An estimate does not need to be exact. It is built from own manufacturing experience, other quotations and public data on wages and material.

From gap to target price

The target price says where the plant wants to go, in steps the supplier can follow.

For H-200 the first step is EUR 59.28, a reduction of 1.2 percent from a lower scrap allowance and a shorter labor time. That is EUR 0.72 times 24,000 pieces, EUR 17,280 per year. Across all castings the first step is worth EUR 69,120. The remaining gap goes into a joint plan over three years.

The price adjustment formula

Without a rule, suppliers ask for a flat increase on the whole price when material rises. A formula limits the movement to the part that really moved.

New price = base price x (fixed share + material share x material index now / material index base + energy share x energy index now / energy index base).

The shares come from the breakdown: EUR 33.20 of 60.00 is fixed, which gives 0.55. Material is 0.37, energy 0.08. Together 1.00.

An example: the material index rises by 10 percent, the energy index falls by 5 percent. The new price is 60.00 x (0.55 + 0.37 x 1.10 + 0.08 x 0.95) = 60.00 x 1.033 = EUR 61.98. A flat 6 percent would have given EUR 63.60.

Checkpoints for a formula

  • Named indexes from a public source, with base month and review dates.
  • Shares from the cost breakdown that add up to 1.00, with a fixed share that does not move.
  • Both directions. The price falls when the index falls.
  • A threshold, for example 3 percent, below which nothing changes, and a fixed rhythm such as every quarter.

What changes in the relationship

A cost breakdown changes the conversation from how much the supplier will give to where the cost is. Foundries that open their numbers expect something in return: volume, a longer term, fast decisions. That is the deal of the Partner field.

The next part looks at two decisions with an even longer effect: whether to make or buy, and how many sources to use.