The lowest price has won many awards and lost many plants money. Freight, stock in the chain, defects and the cost of qualifying a new supplier do not appear in a unit price. A comparison on total cost puts them on the same sheet.
Know the market first
Before a request goes out, four questions need an answer. How many capable suppliers exist? What drives their price? How full is the market? And how attractive are we as a customer?
For the shaft sleeves of the pump plant in this series, more than 60 machining shops work within 400 km. Capacity was free, and a package of EUR 800,000 is a key account for a shop with 60 people.
From there the list narrows: 14 suppliers on the long list, 9 answers to the request for information, 6 suppliers on the short list, 3 in the final round.
One package for all
A quotation can only be as comparable as the request behind it. Every supplier receives the same package on the same day:
- Cover letter with scope, timetable, contact and the rules of the process.
- Specification: drawings, material, test requirements, packaging.
- Quantities: annual demand per part number, batch sizes, forecast for two years.
- Commercial terms: delivery term and place, payment term, price validity.
- A price sheet and a price breakdown form, the same for all.
The rules of a fair process are short. Same information at the same time for everyone. No price of one supplier is shown to another. And every supplier that quoted gets feedback with the reason for the decision.
Four additions to the price
The comparison adds four elements to the unit price.
- Freight and duty per piece, to the door of the plant.
- Inventory cost: landed price times the carrying cost rate times the days of stock in the chain, divided by the days of the year.
- Quality cost: the defect rate times the cost of one defective part for sorting, rework and line disruption.
- One-time cost: qualification, samples and gauges, spread over the contract term and the quantity.
Agree the rates once with controlling, quality and logistics, and use the same sheet for every award. The plant uses 20 percent carrying cost, 360 days, EUR 20 per defective part and three years.
The shaft sleeves
The annual quantity is 120,000 pieces. Supplier A is the incumbent, 40 km away. Supplier B is regional, 300 km away. Supplier C delivers by sea.
| EUR per piece | A | B | C |
|---|---|---|---|
| Unit price | 8.000 | 7.300 | 6.600 |
| Freight and duty | 0.000 | 0.140 | 0.620 |
| Inventory cost | 0.040 | 0.062 | 0.361 |
| Quality cost | 0.050 | 0.040 | 0.120 |
| One-time cost | 0.000 | 0.040 | 0.100 |
| Total cost per piece | 8.090 | 7.582 | 7.801 |
Behind the additions stand 9, 15 and 90 days of stock and defect rates of 2,500, 2,000 and 6,000 parts per million.
On price, C wins: 17.5 percent below the incumbent and 9.6 percent below B. On total cost, B wins with EUR 909,840 per year. That is EUR 60,960 below A and EUR 26,280 below C.
What the table does not show
Ninety days of stock in the chain are also ninety days of reaction time. A drawing change or a quality problem reaches the plant three months later. That belongs in the decision, even without a number.
The award team of purchasing, engineering, quality and production chose B. In the accounts, the landed price falls from EUR 8.00 to EUR 7.44. That is EUR 67,200 per year, 7.0 percent. Together with the two other part families, the tender is worth EUR 144,000 per year on EUR 2.4 million of spend.
Where it fits
The comparison comes before the final talks, not after. The negotiation itself is a topic of its own. Where no three comparable quotations exist, the next part shows the other way to a fair price: the cost breakdown.