An award is a result of today. A contract decides whether it still holds in two years. This part lists the points purchasing must have answered before a contract goes to legal review. It is a list of checkpoints, not legal advice.
Why frame contracts
A frame contract fixes the terms once, and every delivery is a call-off against it. The price is agreed for a volume, not for a single order, and the call-off needs no buyer.
In the pump plant of this series, 55 percent of the spend was under contract at the start. After twelve months the coverage was 72 percent.
Ten checkpoints
The example is the frame contract for shaft sleeves with the regional supplier that won the comparison on total cost.
| Checkpoint | Question to answer |
|---|---|
| Scope | Which parts, drawings and revision levels are covered? |
| Quantities | Forecast or commitment? Which corridor, and what happens outside it? |
| Term and notice | Start, end, renewal, notice period. |
| Price and adjustment | Fixed for how long, and which formula applies after that? |
| Delivery terms | Which Incoterms rule and place? Who carries freight and risk? |
| Call-offs and stock | Call-off rhythm, minimum quantity, stock at the supplier. |
| Payment | Term and discount. |
| Quality | Agreement, targets, handling of defects and their cost. |
| Tooling and drawings | Who owns tools, gauges and documents? |
| Change and end | Engineering changes, last call-off, return of tools. |
For the shaft sleeves the answers were: 46 part numbers of part family A. A forecast of 120,000 pieces per year with a corridor of 20 percent up and down. A term of 24 months with six months notice. A price fixed for 12 months, then a material formula every quarter. Delivery to the plant with a lead time of 3 weeks. Weekly call-offs and 2 weeks of stock at the supplier. Payment after 60 days. Gauges owned by the plant.
Behind the checkpoints
Quantities are the most frequent source of conflict. A forecast is not a commitment, and the contract should say which of the two it contains. A corridor makes both sides honest. Inside it, the price holds. Outside it, both talk.
Delivery terms decide who pays freight and where the risk passes. Name the rule and the place, and compare quotations only on the same term.
Term and notice are easy to agree and easy to forget. A contract with automatic renewal and a notice period of six months is decided six months before its end, whether anyone looks or not.
What needs legal review
Some points are not for purchasing to word:
- Liability, warranty and penalties, with their limits.
- General terms of both sides, and which apply when both parties refer to their own.
- Competition law: exclusivity, very long terms and exchange of information with other buyers.
- Supply chain duties: due diligence for human rights and the environment, origin and export control, as far as they apply to your company.
Every contract should be reviewed by a qualified legal function before signature. The checkpoints above prepare that review. They do not replace it.
The contract register
A contract that nobody can find protects nobody. One list holds every contract with supplier, category, start, end, notice period and owner. From end date and notice period follows the last day for notice.
The plant found 19 contracts when it built the register. Six had renewed automatically in the last three years because nobody saw the date. One price agreement for seals had already passed its notice date when the list was complete.
Three habits
- Start the contract draft during the tender. Terms that come after the award cost extra.
- Keep price sheets, part lists and forecasts in annexes. They change, the frame should not.
- Review the register every quarter in the category meeting.
The contract secures the price. Whether the price turns into a saving that the accounts show is the subject of the last part.