Strategic Procurement | Part 3 of 8

Category Strategy: Levers, Supplier Base and Targets in EUR

How to write a category strategy on one page, with bundling, specification review, supplier base and targets in EUR.

A savings target of three percent, handed to the buyers in January, produces pressure on suppliers and little else. The same target built from categories, levers and measures produces decisions. The category strategy is the page on which that happens.

Five questions on one page

A category strategy needs one or two pages. It answers five questions.

  • Demand. What do we buy, in which quantities, and how will it develop? Who specifies?
  • Market. Who can supply, how full is the market, and what drives the price?
  • Supplier base. How many suppliers today, how many tomorrow, in which roles?
  • Levers. What will we change?
  • Targets. What is the effect in EUR, by when, owned by whom?

The pump plant of this series started with machined parts, a category in the Bundle field: EUR 4,080,000 of spend, 620 part numbers on own drawings and 41 suppliers. Thirty-six of them share EUR 1,080,000 in single orders at the last price.

Six levers

Every strategy chooses from the same six levers.

  • Bundle demand. Fewer suppliers, larger packages, part families together.
  • Question the specification. Buy what the function needs, standard before special.
  • Widen or change sources. New suppliers, new regions, a second source.
  • Price and cost analysis. Cost breakdown, target price, adjustment formula.
  • Process and logistics. Call-offs, collection routes, catalogs.
  • Contract. Term, quantities, scales, price adjustment.

The first two need no supplier to move first. Both start inside the plant.

Bundling

Bundling groups part numbers by process, size and material into part families and tenders each family as a package. The plant formed three: shaft sleeves with EUR 960,000, flanges and covers with EUR 840,000, bushings with EUR 600,000. The supplier base goes from 41 to 14: three package suppliers, three second suppliers and eight specialists.

Bundling has a limit. A package must still fit several suppliers. A package that only one supplier can deliver removes the competition you wanted to use.

Questioning the specification

Many requirements are habits. Tolerances are copied from older drawings. Purchasing brings three questions to engineering: does the function need this tolerance and surface, could a standard item do the job, and how many materials do we need?

In the plant, 85 part numbers were reviewed. Three steel grades replaced nine, and 14 bushings became catalog sizes. Every change was signed by engineering. The systematic work on functions and their cost belongs to value analysis.

Targets in EUR

Each lever gets a base, an effect, an owner and a start month.

Lever Base (EUR) Effect EUR per year
Bundle demand 2,400,000 6.0 % 144,000
Question the specification 1,200,000 3.0 % 36,000
Logistics: weekly collection route 120,000 20.0 % 24,000
Target of the category 4,080,000 5.0 % 204,000

A target in percent alone invites argument. A target with a base in EUR, confirmed by controlling, does not.

The plant target, built from the bottom

The same page exists for every category. Castings and motors, in the Partner field, aim at 2.0 and 1.5 percent. Freight, sheet metal, MRO, fasteners and packaging aim at 4 to 6 percent through tenders, catalogs and fewer suppliers. Seals and bearings and energy carry no savings target. Their goal is supply.

Added up, the ten categories give EUR 758,400 per year, 3.16 percent of the purchasing volume. Nobody chose that number. It is the sum of eleven measures.

What makes a strategy hold

Three things separate a strategy from a wish list. The requesters took part. Every lever has an owner and a start month. And management approved the targets, so that the buyer can tell 27 suppliers that no new orders will follow.

The next part takes the first lever to the market: the request for quotation and the comparison on total cost.