A plant that treats fasteners like castings wastes buyer time on the first and takes risks on the second. Categories and a portfolio prevent both.
What a category is
A category is a group of items that one supply market can deliver. Not an account, not a department.
Three rules keep the structure usable:
- Form categories by supply market. Turned parts from own drawings are one market, catalog fasteners another.
- Keep the number manageable. Between 8 and 15 categories fit a plant. Below 1 percent of spend, merge.
- Give each category one owner in purchasing and a partner on the side of the requester.
The pump plant of this series formed 10 categories from EUR 24.0 million of spend.
Two axes, seven criteria
Two questions sort the categories. How hard is it to get? And how much does it move the result? Each question becomes an axis, scored from 1 to 5 on written criteria.
Supply risk has four criteria: the number of qualified sources, the time needed to switch, the state of the supply market and how special the specification is. One source or more than twelve months to switch scores 5.
Influence on the result has three criteria: the share of spend, how strongly the price moves the product cost, and the effect on delivery and quality of the finished product. A share of 15 percent or more scores 5, from 10 percent 4, from 7 percent 3, from 4 percent 2.
Each axis is the average of its criteria. From 3.00 upward it counts as high. Portfolios of this kind are known in the literature, for example as the Kraljic matrix. The criteria and the field names used here are our own working version.
Four fields, four directions
The two axes give four fields. Each field has a direction, not a finished strategy.
- Bundle: high influence, low risk. Use the competition: bundle volume, tender, standardize, set target prices.
- Partner: high influence, high risk. Work on cost together: long agreements, cost breakdown, price formula, a second source per part family.
- Secure: low influence, high risk. Availability before price: stock agreements, approved alternatives, longer terms.
- Simplify: low influence, low risk. Cut the effort: few suppliers, catalogs, bin systems, consolidated invoices.
The portfolio of the plant
Purchasing scored the categories in one afternoon together with engineering, production and logistics.
| Category | Field | Influence | Supply risk |
|---|---|---|---|
| Castings | Partner | 5.00 | 4.25 |
| Machined parts | Bundle | 4.33 | 2.25 |
| Electric motors | Partner | 4.33 | 3.50 |
| Sheet metal and welded parts | Bundle | 3.33 | 2.00 |
| Seals and bearings | Secure | 2.67 | 3.50 |
| Freight | Bundle | 3.00 | 1.25 |
| MRO and tools | Simplify | 1.67 | 1.25 |
| Energy | Secure | 2.67 | 3.00 |
| Fasteners and standard parts | Simplify | 1.67 | 1.00 |
| Packaging | Simplify | 2.00 | 1.75 |
Bundle holds EUR 8.16 million with 94 suppliers, Partner EUR 9.12 million with 10, Secure EUR 3.12 million with 11 and Simplify EUR 3.60 million with 225.
How to read it
Bundle is where competition pays first: a third of the spend with low risk and too many suppliers. Partner needs facts before talks, because the plant cannot simply change the foundry. Secure is about supply, and a savings target there sends the wrong signal. Simplify should cost as little buyer time as possible.
Mistakes to avoid
Scoring alone in purchasing is the first. Let the requesters score the effect on the product, and let purchasing score the market. Differences of two points or more are discussed, not averaged.
The second mistake is to treat the field as a verdict. A category moves. A second approved foundry lowers the supply risk of castings. A package that only one supplier can deliver moves machined parts from Bundle to Partner.
The portfolio only sorts. The next part turns one field into a category strategy with levers and targets.