A change process produces a few dates per change: requested, decided, effective, closed. Kept in one register, these four dates are enough to steer the whole process.
Six key figures
Three figures show speed, three show quality. These are the values of the pump plant at the start.
| Key figure | Target | Today |
|---|---|---|
| Lead time per change in working days | 40 | 74 |
| Open changes | 15 | 28 |
| Share of rush changes | Below 15 % | 33 % |
| Decided at first presentation | 85 % | 52 % |
| Complete at closure | 95 % | 55 % |
| Residual stock cost per year in EUR | 31,000 | 86,000 |
Lead time per change
Lead time is counted in working days from the request to the closure. The average of 74 days hides more than it shows, so the plant splits it twice.
By phase: 21 days from request to decision, 38 from decision to effective date, 15 from effective date to closure.
By class: class A changes with customer and tooling took 127 days, class B 85 days, class C 30 days. The targets are 75, 45 and 10. A documentation correction that takes 30 working days is not slow because it is difficult.
Open changes
28 changes were open, 9 of them for more than 90 working days. The number is not independent of the lead time. With 8 changes per month and 21 working days per month:
8 x 74 / 21 = 28 open changes.
Whoever halves the lead time halves the pile. The oldest five open changes are on the agenda of every monthly review until they are closed or stopped.
Share of rush changes
A rush change is introduced before evaluation and decision. 32 of 96 changes were rush changes, 33 percent, and they caused EUR 61,000 of the EUR 86,000 residual stock cost.
The share is a mirror of the normal path. When a decision takes 21 days, people go around the process. The target of below 15 percent is reached by speed, not by prohibition.
The three quality figures
- Decided at first presentation shows whether evaluations are complete when they reach the board.
- Complete at closure comes from a monthly audit of three closed changes at the station, in the system and in the warehouse.
- Residual stock cost adds scrap, rework and supplier fees for old parts, booked to the change that caused them.
For change EC-118, the O-ring groove that runs through this series, the figures were 53 working days of lead time against a class A target of 75, a decision at the first presentation, a complete closure and EUR 2,310 of residual stock cost instead of EUR 7,120.
The monthly review
The board takes 30 minutes once a month with the plant manager: the six figures, the oldest five changes and one countermeasure.
Twelve months
The plant introduced the process in four steps: register, request and board in the first quarter, effectivity rule and document list in the second, approval scopes and supplier agreements in the third, key figures and closure audit in the fourth.
- After 3 months: 66 days, 25 open, rush share 29 percent.
- After 6 months: 55 days, 21 open, 22 percent.
- After 9 months: 46 days, 18 open, 17 percent.
- After 12 months: 39 days, 15 open, 13 percent.
Residual stock cost fell from EUR 86,000 to EUR 31,000 per year. No investment was needed. The effort was a coordinator with about eight hours per week and 45 minutes of board per week for six people.
The first figure to measure is the simplest one. Count the open changes in every department’s list. If nobody knows the number, that is the finding.