A machine that passed the factory test can work. It has not yet shown that it works in your plant, with your media, your data and your people, hour after hour.
The site acceptance test
The site acceptance test, in short SAT, takes place after assembly and commissioning in the plant. It covers what could not be tested at the supplier and what transport may have changed: safety functions, interfaces, documents and training.
The assembly cell AC7 had 20 test points at this stage. Eighteen passed. Two failed: the traceability record carried 12 of 14 fields, and the compressed air consumption was 610 liters per minute where 550 were specified. With three further observations, five new points went into the open points list.
The performance run
The performance run proves the output over time. Its rules are in the specification:
- The plant operates, the supplier watches. Supplier staff may repair, and every intervention counts as a technical stop.
- Every stop is logged with start, end, station and cause, and classed as technical or organizational on the same shift by both sides.
- No tuning during the run. A change to program or parameters restarts the count.
AC7 ran for ten shifts of 450 minutes with two plant operators per shift. Of 4,500 planned minutes, 288 were technical stops and 162 were organizational stops such as missing material. In the remaining 4,050 minutes the cell made 9,800 units, 9,672 of them good at first pass.
| Performance data | Criterion | Result |
|---|---|---|
| Cycle time | At most 25.0 s | 24.8 s |
| Technical availability | At least 92 % | 93.6 % |
| First pass yield | At least 98.5 % | 98.7 % |
| Good units on the lowest day | At least 1,800 | 1,854 |
All four performance data were reached. The process capability on 125 units was 1.71 and 1.58, above the required 1.33.
Final acceptance and open points
Over the whole project, 28 open points were logged: 23 at the factory test and 5 on site. Final acceptance was signed in week 37, one week after plan, when all 3 points of class A and all 15 of class B were closed. Of the 10 points of class C, 7 were closed. The other 3 are listed in the acceptance certificate with dates.
What the acceptance certificate must contain and which legal effects it has depends on your contract and should be checked by purchasing and legal counsel.
Handover to production and maintenance
The project ends when the users have taken over. For AC7 the handover package had five elements, each with a signature:
- Documentation as built: 14 of 14 documents.
- Training: 8 operators and 4 maintenance technicians with signed records.
- Spare parts: 62 items for EUR 35,000 in the store and in the system.
- Maintenance plan: 38 tasks loaded into the maintenance system.
- Program: source code and backup filed, restore tested on site.
The warranty period
Three routines turn a warranty period into something the plant can use.
A fault log from day one, with date, station, cause, response time and the decision whether it is a warranty case. In the first six months of AC7, 19 faults were logged: 14 warranty cases, 3 operating errors and 2 wear parts.
A monthly look at the performance data. The technical availability of AC7 rose from 93.1 percent in the first month to 95.7 percent in the sixth.
A review three months before the end, so that claims reach the supplier in time.
The last step
Within four weeks after final acceptance, the team met for a lessons session. Every lesson became a line in the requirement template or the test protocol.
The previous cell reached its output 14 weeks late and cost EUR 86,000 in retrofits. AC7 was one week late and cost nothing beyond the order. The difference was not the supplier. It was 64 requirements, each with a number and a test.