Integrated Management Systems | Part 5 of 6

Combined Audits and One Management Review

How one audit program covers all topics with one visit per process, how the auditor pool changes and what the agenda of a common management review looks like.

Audits and reviews are where separate systems are felt most. An area that is audited four times a year by four people answers many questions four times. A management team that reviews each topic alone never sees where two topics pull in different directions.

One program, one visit per process

The hydraulic cylinder plant had four audit programs with 42 audit days per year: 18 for quality, 8 for environment, 10 for safety and 6 for energy. Counted by process, that was 42 separate visits by single auditors. The combined program plans one visit per process by a team of two.

Process Days before Days after
Machining 6.0 3.5
Welding and painting 6.5 3.5
Management system and improvement 4.5 1.5
Maintenance 3.5 2.5
Eight further processes 21.5 15.0
Total per year 42 26

Machining used to see four auditors on six days with four reports. Now a team spends 3.5 days there once a year, and the last half day belongs to the findings and the process owner.

The auditor pool

Before, the plant had eleven auditors in four pools, each qualified for one topic. Now it has eight in one pool. Each is qualified for the audit method and for at least two topics, and the two members of a team cover every topic of the process between them.

The question set changes as well. Instead of one checklist per topic there is one set per process, built from its description. Each question carries its topic, so the report can still be sorted by quality, environment, safety and energy.

What only a combined audit finds

The first combined cycle produced 64 findings: 22 on quality, 13 on environment, 19 on safety and 10 on energy. Nine of them sat between two topics. One example: a coolant that quality had approved and that nobody had checked as a hazardous substance.

Every finding carries topic and process, is rated on one scale and goes into the one action register. The process owner answers it, not the representative of the topic.

One management review

The plant held four reviews per year, each of three hours, with the same eight managers. Together they produced six decisions that had an owner, a date and resources. The common review lasts four hours and is held twice a year.

Agenda item Minutes
Decisions of the last review and their status 15
The objective sheet: twelve objectives, all topics 40
Customers and other parties 20
Events and their causes, all topics together 30
Audit results and checks of the requirements 30
Building blocks: what changed 30
Changes ahead 20
The system itself: effort, documents, auditors 15
Decisions with owner, date and resources 40

The agenda has no block per topic. Each item looks at all topics together. Item four, for example, puts defects, accidents, near misses and environmental incidents on one page and asks for common causes.

Rules that make it work

  • Numbers before the meeting. The input goes out one week ahead. The meeting is for questions and decisions.
  • Conflicts on the table. The coordinator names where two topics pull in different directions. A low-solvent paint lowers emissions and needs a longer drying time: the review decided a trial on one line with quality, environment, energy and capacity figures in one table.
  • Decisions into the register. Each decision goes into the action register on the same day.

The first common review ended with eleven decisions.

The effect in hours

Internal audits fall from 1,008 to 624 hours per year, at 24 hours per audit day. The reviews fall from 256 to 160 hours. Together that is 480 hours, more than a third of the whole saving of the merger.

Whether the certification body also audits the merged system in one go is its own decision. How to prepare that question, and how to keep the system integrated, is the subject of the last part.