Integration is often misread as one thick manual that contains everything. The opposite is true. An integrated management system is thin where the topics are alike and deep where they differ. The art is to draw the line between the two.
Topics and mechanism
Quality, environment, safety and energy are topics. A management system is the mechanism that handles a topic: someone sets direction, processes are described, documents are controlled, audits check, actions follow, management reviews. A plant needs every topic. It needs the mechanism only once.
The test for every activity is one question: would we do it the same way whatever the topic? If yes, it belongs to the common core. If it needs a method and a qualification of its own, it is a building block.
Sixteen common elements
The hydraulic cylinder plant of this series listed its elements in its own words and found sixteen that work the same way for every topic.
- Direction: policy, objectives and programs, roles and representatives, scope and expectations of parties.
- Core routines: process landscape and descriptions, control of documents and records, training and briefing, communication and reporting.
- Operations: purchasing and contractors, change management, emergency preparedness, legal and other requirements.
- Check and decide: monitoring and key figures, internal audit, incident, nonconformity and action, management review.
Releasing a document, planning an audit or following an action to its effect does not depend on whether the subject is a weld seam, a solvent or a fall hazard. These elements need one version each. Use the words of your plant, not the chapter structure of a standard.
Four building blocks
Four things stay subject work, each with its own method and its own specialist.
| Building block | What it hands to the core |
|---|---|
| Quality planning and inspection | Control points per process |
| Environmental aspects | Significant aspects per process |
| Hazard assessment | Measures and instructions per workplace |
| Energy review | Large energy uses per process |
Nobody merges a hazard assessment with an inspection plan. The methods differ, the knowledge differs, and the people who do the work must be qualified for it. What the core needs is the result.
Where a building block docks
Each block connects to the core in five places.
- The process description lists control points, aspects, hazards and energy uses of the process on one page.
- The objective sheet takes the objectives that follow from the assessments.
- The register of requirements holds what laws, permits, customers and the group demand.
- The training matrix holds the instructions and qualifications per area.
- The audit question set of each process contains questions from every block that applies.
In the plant, the description of welding and painting now names the weld seam test and coating thickness, solvent emissions and paint sludge, welding fumes and the handling of tubes up to 180 kg, and the drying oven as a large energy use. The assessments behind these points stay with the specialists.
One role model
Four representatives who report to four managers write four sets of rules. The plant replaced this with one model.
- Top management owns policy, objectives, review and resources.
- One coordinator owns the common core and reports to the plant manager.
- Subject specialists own the building blocks, advise the process owners and audit their topic.
- Process owners own everything that happens in their process, for all topics.
Where a law, a permit or a contract requires a named person with a defined duty, that appointment stays as it is. The model changes who maintains the system, not who holds a statutory duty.
What integration does not do
- It lowers no requirement. Every topic keeps its depth.
- It removes no specialist. The safety specialist of the plant handed over 58 common documents and kept 70 on hazards and measures.
With the line drawn, the plant could compare its four systems element by element. The tool for that is the overlap matrix in the next part.