Integrated Management Systems | Part 1 of 6

What Separate Management Systems Cost

Why plants end up with several management systems side by side, what exists several times and how to calculate the upkeep in hours and EUR.

Nobody decides to run four management systems. They arrive one by one. A customer asks for a quality certificate, a permit brings environmental duties, an accident leads to a safety system, a group rule adds energy. Each system is built by a different person in a different year, and each one is right for its time. Ten years later the plant has four policies on four notice boards.

The example plant

This series follows a plant that makes hydraulic cylinders: machining, welding, painting and assembly, 320 employees, EUR 58 million in sales. It runs four systems, built one after another since 2012: quality, environment, occupational health and safety, and energy. The standards behind them, such as ISO 9001, ISO 14001, ISO 45001 and ISO 50001, are mentioned here by name only. Everything in this series uses its own structure and words.

What exists several times

The first step is to count. The plant’s count surprised the people who had built the systems.

What exists several times In the plant
Policies 4
Controlled documents 500
Of these on the same 16 subjects 228
Internal audit days per year 42
Audit days of the certification bodies 14
Management reviews per year 4
Objectives, in four lists 27
Open actions, in four lists 110

The effect on the shop floor is easy to see. Machining is visited four times a year by four auditors with four checklists. The same eight managers sit in four reviews of three hours each. Of the 110 open actions, 41 are overdue, and nobody can say which of them matters most, because each list has its own priority.

Contradictions

Duplication costs hours. Contradiction costs trust. When the plant laid its rules side by side, it found seven cases where two systems demanded different things of the same person. Training records were to be kept for three, five or ten years, depending on the procedure. A new chemical needed the approval of the environmental officer on one form and of the safety specialist on another, and purchasing used neither. A rule that contradicts another rule is broken whatever people do.

The upkeep in hours

The plant calculated what it costs to keep four systems alive. Subject work, such as inspections, hazard assessments or energy measurements, is not included. The figure covers only the mechanism.

Item Calculation Hours
Maintaining documents 500 documents x 1.5 hours 750
Internal audits 42 audit days x 24 hours 1,008
Accompanying external audits 14 audit days x 16 hours 224
Management reviews 4 reviews x 64 hours 256
Tracking objectives 4 lists x 12 months x 6 hours 288
Registers of requirements 3 registers x 4 updates x 16 hours 192
System briefings 4 briefings x 320 employees x 0.25 hours 320
Total per year 3,038

An internal audit day counts 24 hours: 16 for the auditors with preparation and report, 8 for the audited area.

At EUR 60 per hour, 3,038 hours are EUR 182,280. The certification bodies charge 14 audit days at EUR 1,450, which adds EUR 20,300. The four systems cost EUR 202,580 per year before a single hazard is assessed or a single part is inspected.

What the number is for

The figure is not an accusation. It shows what the plant pays for running the same mechanism four times. That is the part that can be merged.

How to start

  • Give each representative the same list of questions and half a day.
  • Count what is controlled: documents with a number, a version and a release.
  • Take audit days from the programs and the plans of the certification bodies, not from memory.
  • Put the four pages on one table and add the totals.

The count ends the discussion about who has the larger system. It starts a better one: which of these things does the plant need once, and which does every topic need for itself? That is the subject of the next part.