Sixteen elements cannot be merged at once. The merger works when it is cut into waves, each of which leaves the plant in a state that can be audited.
Three questions for the order
The hydraulic cylinder plant sorted its elements by three questions: how much duplication is there, how little dispute, and what do the later elements need first?
| Wave | Months | Elements | Documents |
|---|---|---|---|
| 1 | 1 to 3 | Policy, roles, control of documents, events and actions | 61 to 12 |
| 2 | 4 to 6 | Scope, process descriptions, objectives, requirements, training | 62 to 25 |
| 3 | 7 to 9 | Internal audit, communication, purchasing, change, emergency, key figures | 95 to 23 |
| 4 | 10 to 12 | Management review, combined external audit | 10 to 2 |
Wave 1 builds the tools that every later merge needs. Wave 2 builds the frame that audits and the review will look at. Wave 3 merges what happens in the areas and needs the most time of the process owners, so it is planned outside the peak season. Wave 4 closes with the first common review. Over the four waves, the documents on common subjects fall from 228 to 62.
Roles before documents
The first decision of wave 1 is the role model. The plant named one coordinator for the common core, who reports to the plant manager. The four subject specialists keep their building blocks. Twelve process owners answer for their processes in all topics. Coordinator and specialists form the system team, which meets every two weeks for 45 minutes and decides on merged rules.
How documents are merged
A merged document is shorter than the sum of its predecessors. Five rules make sure of that.
- One document per subject. Topics appear as a field or a short section only where they differ.
- Start from the best version. Take the rule the areas actually use, whichever system owns it.
- Subject content moves out. What only one topic needs goes into its building block or the process description.
- Duties move to the register. What authorities or customers demand becomes an entry in the register of requirements.
- Withdraw on the same day. A merged document that exists beside its four predecessors is a fifth version.
The path for events shows the effect. The plant had four procedures with 27 pages, ten forms and four action lists: 18 documents. The steps were the same in all four: report, contain, find the cause, act, check the effect. Now there is one procedure of 7 pages, one report form with a topic field and one action register. When the 110 open actions were moved into it, 19 turned out to be listed twice.
The transition
- Tell the certification bodies about the project before the next audit. The certificates stay valid while you merge.
- Switch one element at a time. Between two waves, the plant runs a mix of merged and separate elements, and the overlap matrix shows the state.
- Let audits run on with the old programs through waves 1 and 2. The combined program starts in wave 3.
The effort
| Item | Hours |
|---|---|
| Core team: coordinator and four specialists | 620 |
| 12 process owners, 20 hours each | 240 |
| Merging documents with the areas | 380 |
| Training 8 auditors, 16 hours each | 128 |
| Four steering meetings of eight managers | 32 |
| Total | 1,400 |
At EUR 60 per hour this is EUR 84,000. An auditor course and the migration of documents add EUR 11,200. The one-time effort is EUR 95,200.
What it pays
After the merger, the upkeep of the system falls from 3,038 to 1,761 hours per year and from EUR 202,580 to EUR 118,710. The saving of EUR 83,870 per year gives a payback of 13.6 months. The hours are not cut from the payroll. They move from paperwork to subject work on the shop floor.
The largest single saving comes from the audits. How one program replaces four is the subject of the next part.