Before anything is merged, the systems are compared. The tool is a simple matrix: the elements of a management system as rows, your systems as columns. Each cell answers one question: does this system have its own version of this element?
Start with the inventory
The matrix needs numbers behind it. The hydraulic cylinder plant counted each of its four systems with the same questions.
| What was counted | Total |
|---|---|
| Controlled documents (214, 96, 128 and 62) | 500 |
| Of these on common subjects | 228 |
| Internal audit days per year | 42 |
| Objectives | 27 |
| Open actions | 110 |
Every controlled document is marked as common subject or subject work. A procedure for audits is common, an inspection plan is subject work.
Four codes per cell
The four specialists fill the matrix together in one session of about three hours.
- O: the system has its own version. An O needs a controlled document on the table, not a habit.
- S: the system uses the version of another system.
- G: gap. The topic needs the element and no version covers it.
- A dot: not applicable.
Behind each O, the team notes the number of documents.
The result in the plant
Part of the plant’s matrix looked like this.
| Element | Quality | Environment | Safety | Energy |
|---|---|---|---|---|
| Policy | O | O | O | O |
| Control of documents | O | O | O | O |
| Process descriptions | O | S | G | G |
| Change management | O | G | O | G |
| Legal and other requirements | G | O | O | O |
Over all sixteen common elements, the plant counted 52 own versions. One version per element would be enough, so 36 are duplications. Eight elements existed four times: policy, objectives, roles, control of documents, key figures, internal audit, the path for events and actions, and the management review. These eight are the first candidates for a merge.
The documents follow the same pattern. The 228 documents on common subjects sit behind those 52 versions. The largest piles were key figures with 24 documents, control of documents with 21 and purchasing and contractors with 19.
The eight gaps
The matrix also shows where a topic is exposed. The plant found eight gaps.
- Safety had never described who expects what of the plant.
- The process descriptions named quality and environmental points, but no safety and no energy points.
- No rule said who reports energy data to whom.
- Equipment was bought without energy criteria.
- Changes to plant and materials were checked for quality and safety, and for environment and energy by nobody.
- Statutory and customer requirements on the product were in no register.
A gap is not a failure of the person who built the system. Each system was built for its topic at its time. But the two kinds of findings differ in weight. A duplication costs hours. A gap can cost a permit, a customer or an injury.
Gaps first
The plant decided to close each gap with the merge of the element, not after it. The merged change procedure checks all four topics from its first day. The merged process description has a section for each topic. This way the merger pays twice: less paper and fewer blind spots.
From matrix to target
For each row the team sets a target: one version for a common element, or building block for subject work. Then it estimates the documents after the merge. In the plant, the 228 documents on common subjects become 62. Of the 272 documents of subject work, 24 turned out to be obsolete, which leaves 248. The target is 310 documents instead of 500.
Rules for the session
- Use your own element names. Do not copy the structure of a standard into the rows.
- Look at the document when two people disagree about a cell.
- Keep the matrix. It is updated after every merge and shows the state of the system at any time.
The matrix tells the plant what to merge. The order, the roles and the effort are the subject of the next part.