Lean and Green | Part 10 of 10

Lean and Green on the Shop Floor Board

Four figures per area, five routines and a twelve-month roadmap keep energy, material and water steered like output and quality.

Energy reports that go to management once a month change little. The figures need to be where the people who switch machines on and off look every day: on the shop floor board.

Four figures per area

In the example plant every area board shows four figures next to output, quality and delivery:

  • Energy per good part: target from 10.0 to 8.0 kWh within twelve months, reviewed weekly.
  • Weekend base load: target from 280 to 160 kW, written every Monday.
  • Open leak tags: none older than two weeks.
  • Scrap rate of the worst line: line 3 from 3.2 to 1.2 percent, daily.

Monthly figures for the plant add CO2e per good part, water per 1,000 parts and non-recycled waste per part.

Five routines

  • Shutdown standard at the end of the last shift on Fridays and before holidays, signed by the team leader.
  • Base load reading by maintenance every Monday morning.
  • Resource walk without production once a month, rotating through the halls.
  • Board review in the weekly shop floor meeting, five minutes.
  • Measure review with plant manager, energy owner and controller once a month.

Five minutes in the weekly meeting

The board review follows five questions, one minute each: energy per part against target, Sunday base load, old leak tags, scrap on the worst line, and one idea from the team to try this week. If an answer is bad, the action gets an owner and a date before the meeting moves on.

Roles

Lean and Green fails when it belongs to one person. The plant manager sets targets and decides on the budget. An energy and resource owner, often 20 to 50 percent of one position in a plant of this size, runs the data, the measure cards and customer requests. Maintenance owns utilities and leaks. Team leaders own the shutdown standard and the board.

A twelve-month roadmap

  • Months 1 to 3: bills, meter list, base load, energy and CO2 per part, shutdown routine, leak program.
  • Months 4 to 6: energy value stream of the main family, measure cards, quick wins done and verified.
  • Months 7 to 9: heat, water and waste, investment requests with energy and CO2 effect.
  • Months 10 to 12: targets per line for the next year, supplier data for the main materials, repeat the self-check.

Beyond the plant

When the plant numbers are reliable, extend the same method to suppliers. For a machined aluminum part, the material carries roughly three times the CO2e of the plant. Ask the largest material suppliers for their own data, agree on recycled content and design parts closer to their final shape.

Start in the plant, where you have control and credibility. Then the customer questionnaire becomes a two-day task, and the board keeps the savings from drifting back.