Planning and scheduling are often used as one word. They are two different jobs. Planning decides how a job is done. Scheduling decides when. Both happen before the week starts, and both are done by a planner who does not repair.
What a prepared job contains
For a spindle bearing change on a machining center, the job plan lists:
- 14 steps from lockout to test cut, with torque values and checks,
- 2 mechanics for 6 hours and 1 electrician for 2 hours,
- the bearing kit, seals and grease, reserved in the storeroom,
- the spindle lifting device, a torque wrench and a dial gauge,
- lockout points, the permit and a lifting plan,
- the production window: Saturday early shift, agreed with production.
A technician who starts this job finds everything ready. That is where the hours come from.
Capacity first
The weekly schedule starts with honest capacity. For one area with eight technicians:
| Item | Hours per week |
|---|---|
| 8 technicians x 37.5 hours | 300 |
| Minus absence, training, meetings (12 percent) | 36 |
| Available hours | 264 |
| Reserve for emergencies (25 percent) | 66 |
| Hours to schedule | 198 |
Load the schedule with 70 to 85 percent of the available hours. Emergencies will come, and the reserve absorbs them without breaking the plan. A schedule loaded to 100 percent is broken on Monday morning.
The weekly rhythm
- Wednesday: the planner drafts the schedule from the ready backlog, priorities and production windows.
- Thursday: a 30-minute meeting with production and the maintenance supervisors agrees the schedule.
- Daily: supervisors assign jobs from the schedule. Emergencies use the reserve.
- Friday: schedule compliance is measured, with a reason for every missed job.
Schedule compliance
Schedule compliance = done hours of scheduled jobs / scheduled hours. In the example area, 77 of 120 scheduled hours were done in the first measured week: 64 percent. The reasons were familiar: emergencies took the people, parts were missing, the machine was not released by production.
Each reason points to a fix. Missing parts mean the job was not really ready. Machines not released mean the production window was not agreed. Emergencies mean the reserve was too small or the strategy for some assets is wrong.
Protect the planner
The most common failure is a planner who is pulled into breakdown repairs whenever it gets busy. One extra pair of hands helps for an hour. A prepared job saves hours every day. A rule of thumb is one planner for 15 to 25 technicians.
Production as a partner
The weekly schedule is a contract between maintenance and production. Production gives fixed windows: shift changes, a monthly Saturday shift for A assets, planned stops. Maintenance promises that prepared jobs fit into them and that the asset is back on time. Both sides measure it every Friday.
The next part shows how to measure the stock of prepared work: the backlog in weeks.