Two problems live in most maintenance storerooms at the same time. The bearing kit for the bottleneck machine is missing on the night it is needed. And the shelves hold parts for machines that were scrapped years ago.
Both have the same cause: stock that follows habit instead of rules.
Four classes of parts
| Class | Example | Rule |
|---|---|---|
| Critical | Failure stops an A asset, lead time above one week | On site, reorder point, checked monthly |
| Wear | Seals, belts, filters with regular usage | Reorder point from usage and lead time |
| Standard | Available from a supplier within 24 hours | No stock or minimal stock, supplier agreement |
| Insurance | Rare, very long lead time, very expensive | Decision by plant management, possibly shared between sites |
The class of the part follows the class of the asset it belongs to. A seal for an A asset with a lead time of eight weeks is critical. The same seal for a C asset with two identical machines next to it is standard.
The reorder point
Reorder point = usage during the lead time + safety stock.
Example, spindle bearing kit for the bottleneck machining center: usage 6 per year, lead time 8 weeks. Usage during the lead time = 6 x 8 / 52 = 0.9, rounded up to 1. Safety stock for an A asset = 1. Reorder point = 2.
When the stock reaches 2, the next kit is ordered. A maximum of 3 prevents the shelf from filling up. In the example plant, the stock was 1 at the time of the review: one bearing failure away from an emergency delivery.
For parts with very irregular usage, use judgment instead of the formula, and document the decision.
Stock without movement
In the example plant the storeroom held EUR 1.9 million, and 31 percent of the value had not moved for more than three years. Typical causes: parts for machines that were sold or scrapped, initial spare packages bought with new equipment, and orders placed “just in case” after one bad experience.
A yearly review with maintenance, purchasing and controlling decides for each slow mover: keep, return to the supplier, sell, scrap, or share with another site. The first review in the example plant freed EUR 240,000 and moved the remaining slow movers into a separate area with a decision date.
Find a part in five minutes
A part that cannot be found is not in stock. The storeroom needs fixed locations, labels, a booking for every withdrawal and one person responsible. Parts reserved for a planned job are picked and put into a job box before the job starts. The technician should find a part in less than five minutes, at any time of day.
Work with purchasing
Lead times for drives, controls and special parts have grown in recent years. Agree with purchasing which parts count as critical, review their lead times twice a year, and look for consignment stock or framework agreements for wear parts. The reorder point is only as good as the lead time behind it.
The next part covers the other scarce resource: skilled hours, inside and outside the plant.