The scarcest resource in maintenance is no longer money. It is skilled hours. Experienced technicians retire, new ones are hard to find, and the equipment contains more drives, controls and software every year.
Two questions follow: who in the team can do what, and what should be done by someone outside the team?
The skill matrix
Rows for tasks, columns for people, a level per cell:
- 0 none,
- 1 in training,
- 2 with support,
- 3 alone,
- 4 can teach others.
Count for every task how many people reach level 3 or 4. Fewer than two is a gap. In the example area, two tasks had a gap: vibration measurement, which only one technician could do, and test bench calibration. Both belonged to A assets, so they were trained first.
Plan at least 40 hours of training per person and year, and schedule it like a job. Training that is planned “when it gets quieter” never happens.
Roles in the team
A plant with 22 technicians typically needs:
| Role | Number | Main task |
|---|---|---|
| Maintenance manager | 1 | Strategy, budget, people, interface to plant management |
| Supervisor per shift | 3 | Daily assignment, emergencies, safety |
| Planner | 1, later 2 | Job preparation, weekly schedule, data quality |
| Reliability engineer | 1 | Strategies, bad actors, root cause, condition monitoring |
| Technicians | 22 | Execution, feedback, improvement ideas |
The reliability engineer is the role most often missing. Without it, nobody has time to ask why a failure keeps coming back.
Keep knowledge in the system
When a technician with 30 years of experience retires, much of what he knows about the bottleneck machine leaves with him. Job plans, repair notes in the work orders and photos of tricky steps keep part of it. Plan retirements 18 months ahead and pair the experienced technician with a successor on the A assets.
Service providers
External providers make sense for:
- specialized tasks such as elevators, cranes, fire protection and high voltage,
- peak work during shutdowns and overhauls,
- tasks that require certified providers under your local rules,
- calibration of measuring equipment.
Keep in house: breakdown response on A assets, planning and scheduling, root cause analysis of repeat failures, and the knowledge of the bottleneck equipment.
What every service agreement needs
- the scope as a list of assets, tasks and exclusions,
- response and repair times by priority, with measurement,
- feedback on work orders in your system, not only invoices,
- a performance review twice a year with numbers.
In the example plant, service providers accounted for 18 percent of the maintenance cost. The review showed that two contracts covered the same compressors. Contract wording itself is a matter for your purchasing and legal departments.
The last block of this series turns to the numbers that show whether all of this works.