Rough Cut Capacity Shows the Peak While It Is Still Cheap

Convert the demand plan into hours on the bottleneck, compare with available hours, and solve the peaks three months ahead.

Most capacity problems are found in the week they happen. By then the only options are overtime, express freight and angry customers. A rough cut capacity check finds them months earlier.

Units into hours

Take the demand plan per family and month, multiply by the hours per unit on the bottleneck, and add up. In the pump example, assembly is the bottleneck with 1.5 hours per compact pump, 6 hours per process pump and 120 hours per engineered system.

For the first half of 2027:

  • January: 8,820 hours required, 93 percent of 9,500 available
  • February: 9,090 hours, 96 percent
  • March: 9,600 hours, 101 percent
  • April: 10,020 hours, 105 percent
  • May: 10,530 hours, 111 percent
  • June: 9,810 hours, 103 percent

Over six months the plan needs 57,870 hours against 57,000 available, only 1.5 percent more. The problem is not the total, it is the timing.

Available means available

Available hours are people times shift hours, minus absence, training and planned maintenance. Not the theoretical maximum of the equipment and not the head count on paper.

Check every critical resource: the bottleneck and every resource above 85 percent load in any month. Usually two to five resources are enough. Add critical materials with long lead times or single suppliers, with the capacity the supplier has confirmed.

Options with cost

For the May peak, the supply review prepared three options:

  • Correct the process pump bias by 5 percent after review with sales: May load from 111 to 109 percent, no cost.
  • Pre-build 250 compact pumps in January and February each and take them out of April and May: May load to 105 percent, seasonal stock of up to 500 units, about EUR 260,000 tied up for three months.
  • Two Saturday shifts in May for the remaining 450 hours, with an overtime premium and the agreement of the works council.

The executive review chose all three. Every option has a cost, an owner and a date.

Mark both ends

Months above 95 percent need attention, months above 100 percent need a decision. Months below 75 percent matter too: they are the room for pre-building, maintenance, training and improvement work. Showing both ends turns the capacity check from a warning list into a planning tool.

Materials are capacity too

In the example, the motor supplier confirms 600 motors per month, while process pumps need 646 in May. Pulling 50 motors ahead in April costs an express surcharge of about EUR 4,500. Found in May, the same gap would stop the line.

Rough, not detailed

The check is rough on purpose. It uses families, months and average hours. Detailed sequencing, changeovers and shift plans belong to the master schedule and the shop floor. The rough cut answers one question only: can we deliver the plan with the capacity we have, and if not, what will we do about it, decided now.