Cycle Time, Line Capacity and Staffing Calculator

Checks whether a line can meet demand: capacity from the slowest station, load against demand and the number of operators from the work content.

Your figures

min

Shift length minus breaks and planned stops.

units
s
s

Sum of all manual work elements for one unit.

%

Share of the time that is really productive (small stops, quality losses). 100 means no allowance.

Calculated in your browser. Your figures are neither transmitted nor stored.

Enter your figures and select Calculate. The fields are prefilled with a worked example.

The formula

Use this calculator when you know the takt and want to check whether the bottleneck station and the staffing can deliver the demand.

Line capacity = Available time × Planned efficiency / Bottleneck cycle time

Takt time = Available time / Demand

Planned cycle time = Takt time × Planned efficiency

Operators = Manual work content per unit / Planned cycle time (rounded up)

Worked example

Inputs

  • Available working time per shift: 450 min
  • Demand per shift: 480 units
  • Cycle time of the slowest station: 45 s
  • Manual work content per unit: 190 s
  • Planned efficiency: 90%

Calculation

  1. Takt time = 450 min × 60 / 480 units = 56.3 s per unit
  2. Planned cycle time = 56.3 s × 90% = 50.6 s per unit
  3. Line capacity = 27,000 s × 90% / 45 s = 540 units per shift
  4. Capacity load = 480 / 540 = 88.9%
  5. Operators = 190 s / 50.6 s = 3.75, rounded up to 4

Result

Line capacity: 540 units per shift. The line can meet the demand: the slowest station at 45 seconds is within the planned cycle time of 50.6 seconds, with a reserve of 60 units per shift.

How to read the result

  • The slowest station sets the capacity of the whole line. An hour gained at any other station changes nothing.
  • The planned efficiency covers small stops and quality losses. Do not hide large losses in it: measure them with OEE and remove them.
  • Round the number of operators up. If the calculated value is only a little above a whole number, reduce the work content first instead of adding a person.