Takt Time Calculator
The pace of customer demand: how many seconds you have for one unit so that the daily demand is met exactly.
Enter your figures and select Calculate. The fields are prefilled with a worked example.
How to read it
How it was calculated
Please confirm your newsletter subscription via the link in your inbox.
The formula
Use this calculator when you design or rebalance a line or cell and need the pace that customer demand sets.
Takt time = Available working time / Customer demand
Available working time = Shifts × (Shift length - Breaks)
Worked example
Inputs
- Shifts per day: 2 shifts
- Shift length: 480 min
- Breaks and planned stops per shift: 30 min
- Customer demand per day: 900 units
Calculation
- Available working time = 2 shifts × (480 min - 30 min) = 900 min = 54,000 s per day
- Takt time = 54,000 s / 900 units = 60 s per unit
- Required output = 900 units / 15 h = 60 units per hour
Result
Takt time: 60 s per unit. One unit has to leave the process every 60 seconds. Every station whose cycle time is longer than that cannot keep pace without overtime or a second resource. Plan the cycle time of the line slightly below the takt time to cover small disturbances.
How to read the result
- Takt time is set by the customer, not by the machine. It changes when demand or working time changes, so recalculate it with every new demand plan.
- Compare the takt time with the cycle time of each station. A station above takt is a bottleneck, a station far below takt waits.
- Use the net working time: subtract breaks and planned stops, but not breakdowns or changeovers. Those are losses to remove, not time to plan away.
- Cycle Time and Line Capacity
Checks whether a line can meet demand: capacity from the slowest station, load against demand and the number of operators from the work content.
- Lead Time and Process Cycle Efficiency
Turns the inventory in a value stream into lead time and shows which share of that time adds value.