Takt Time Calculator

The pace of customer demand: how many seconds you have for one unit so that the daily demand is met exactly.

Your figures

shifts
min
min

Breaks, meetings, planned cleaning. Not breakdowns.

units

Calculated in your browser. Your figures are neither transmitted nor stored.

Enter your figures and select Calculate. The fields are prefilled with a worked example.

The formula

Use this calculator when you design or rebalance a line or cell and need the pace that customer demand sets.

Takt time = Available working time / Customer demand

Available working time = Shifts × (Shift length - Breaks)

Worked example

Inputs

  • Shifts per day: 2 shifts
  • Shift length: 480 min
  • Breaks and planned stops per shift: 30 min
  • Customer demand per day: 900 units

Calculation

  1. Available working time = 2 shifts × (480 min - 30 min) = 900 min = 54,000 s per day
  2. Takt time = 54,000 s / 900 units = 60 s per unit
  3. Required output = 900 units / 15 h = 60 units per hour

Result

Takt time: 60 s per unit. One unit has to leave the process every 60 seconds. Every station whose cycle time is longer than that cannot keep pace without overtime or a second resource. Plan the cycle time of the line slightly below the takt time to cover small disturbances.

How to read the result

  • Takt time is set by the customer, not by the machine. It changes when demand or working time changes, so recalculate it with every new demand plan.
  • Compare the takt time with the cycle time of each station. A station above takt is a bottleneck, a station far below takt waits.
  • Use the net working time: subtract breaks and planned stops, but not breakdowns or changeovers. Those are losses to remove, not time to plan away.