Lead Time and Process Cycle Efficiency Calculator
Turns the inventory in a value stream into lead time and shows which share of that time adds value.
Enter your figures and select Calculate. The fields are prefilled with a worked example.
How to read it
How it was calculated
Please confirm your newsletter subscription via the link in your inbox.
The formula
Use this calculator when you have counted the inventory along a value stream and want the lead time and the value-added share.
Lead time = Inventory in the value stream / Demand per day
Process cycle efficiency = Value-added time / Total lead time
Worked example
Inputs
- Inventory in the value stream: 2,400 units
- Customer demand per day: 400 units
- Value-added time per unit: 42 min
- Hours per day for the conversion: 24 h
Calculation
- Lead time = 2,400 units / 400 units per day = 6 days
- Lead time in minutes = 6 days × 24 h × 60 = 8,640 min
- Process cycle efficiency = 42 min / 8,640 min = 0.49%
Result
Lead time: 6 days. A unit needs 6 days to pass through the value stream, and value is added during 42 minutes of that time. For every minute of work the product waits about 205 minutes. An efficiency below 1 percent is common in batch production with large stocks: the lever is inventory between the steps, not faster machines.
How to read the result
- Lead time follows from inventory: at a steady demand, every unit in stock waits until the units in front of it are used. Halving the inventory halves the lead time.
- Use the same time basis as in your value stream map. With calendar time (24 hours) the efficiency looks lower than with working hours; state which one you used.
- Faster machines barely change the result, because processing time is a tiny share of the lead time. Reducing stock between the steps does.