A current state map produces dozens of ideas. The method asks for discipline first: design the future state by answering eight questions in a fixed order, from the customer back to the raw material. Each answer needs a number.
1. Rhythm
How often does the customer need one piece, and can every process keep that rhythm?
Takt time is 54,000 seconds / 450 housings = 120 seconds. Every cycle time is below it. At 20 percent more demand it would be 100 seconds, and assembly needs 105.
2. Finished goods
Do we ship from a finished goods supermarket, or do we build straight to the dock?
Two variants, steady demand and one day of notice speak for a supermarket.
3. Flow
Which steps can be linked so that a piece moves on without waiting?
Continuous flow needs steps with a similar rhythm, short changeovers and good uptime, close together.
- Die casting and trim: yes. The casting operator has 45 seconds free per cycle, trimming takes 40.
- Casting and machining: no. The casting cell is shared and needs 120 minutes per changeover.
- Machining, leak test and assembly: yes. Cycle times of 100, 50 and 105 seconds fit the takt time. They become one cell.
In that cell, the manual work per housing is 25 + 50 + 105 = 180 seconds. At takt time that is work for 1.5 people, staffed with two.
4. Pull
Where flow has to stop, which supermarket or FIFO lane connects the processes, and how large is it?
Three supermarkets remain: raw material, trimmed castings and finished goods.
Maximum = demand per day x (replenishment interval + buffer + safety).
| Item | Interval + buffer + safety | Maximum |
|---|---|---|
| Finished H40 | 1.0 + 0.3 + 0.5 days | 540 |
| Finished H60 | 1.0 + 0.3 + 0.5 days | 270 |
| Trimmed casting H40 | 2.0 + 0.2 + 0.3 days | 750 |
| Trimmed casting H60 | 2.0 + 0.2 + 0.3 days | 375 |
Inside the cell, two FIFO lanes hold at most 60 and 30 pieces. When a lane is full, the process in front of it stops.
5. One schedule
Which single process receives the customer signal and sets the pace for all the others?
The cell becomes the pacemaker. Machining, its first step, gets the only production signal. Everything after it runs in FIFO, everything before it is called by withdrawal. Four schedule points become one.
6. Mix
How often does the pacemaker switch between variants?
Today the smaller variant runs in batches of 300 every second day. The design says every variant every shift: six containers of H40 and three of H60. That needs four changeovers per day.
7. Portion
In which fixed portion of work is the pacemaker released and checked?
The pitch is takt time times pack quantity: 120 seconds x 25 housings = 50 minutes. Every 50 minutes a material handler brings one production card and takes one finished container away. That is 18 checks a day on whether the stream is on time.
8. Enablers
Which process improvements does the design need before it can work?
Only now come the improvement ideas, and only those the answers above require.
| Improvement | Today | Needed |
|---|---|---|
| Machining changeover | 45 min | 15 min |
| Machining uptime | 90 % | 95 % |
| Casting changeover | 120 min | 60 min |
| Casting uptime | 82 % | 90 % |
| Leak test first pass yield | 97 % | 98.5 % |
Four changeovers of 15 minutes take 60 of the 210 free machine minutes that machining has at 95 percent uptime. For the changeover method, see the series on SMED.
Why the order matters
Teams that begin with question 8 collect good projects that do not fit together. Teams that begin with question 1 get a short list in which every item has a reason.