Value Stream Mapping | Part 7 of 8

The Future State Map and Loops: One Schedule, Three Supermarkets

How to draw the future state map, calculate its lead time ladder and cut the design into loops that can be built one after another.

The eight answers from the last part are a design in words. The future state map turns them into a picture the whole plant can read. It shows what the team can reach in about a year with the equipment it has. Then the picture is cut into pieces small enough to build.

The future state in six sentences

  • Shipping takes containers from a finished goods supermarket for the daily truck.
  • Each container taken sends one production card to a leveling box at the cell.
  • The cell machines, tests, assembles and packs in flow, with two operators and two FIFO lanes.
  • The cell withdraws trimmed castings from a supermarket. A signal card at the reorder level starts the next casting batch.
  • Die casting and trim run as one cell with one operator and make every variant every two days.
  • Ingots arrive twice a week into a raw material supermarket with a marked maximum.

In the current state, information lines fan out from production control to four points. In the future state one line runs from the customer to shipping, and from there the signals travel upstream with the material, card by card. Every inventory has a maximum and a rule for what happens when it is reached.

The new ladder

Supermarkets enter the ladder with their average stock: half the replenishment interval plus buffer and safety. FIFO lanes enter with their maximum.

Inventory Pieces Days
Raw material supermarket 900 2.0
Trimmed castings supermarket 675 1.5
FIFO lanes in the cell 90 0.2
Finished goods supermarket 585 1.3
Total 2,250 5.0

The processing time does not change. It is the same 450 seconds, because nobody works faster. Flow efficiency rises from 0.05 to 0.17 percent, and the stream turns 48 times a year instead of 14.5.

Before and after

Measure Current state Future state
Lead time 16.5 days 5.0 days
Inventory 7,425 pieces 2,250 pieces
Schedule points 4 1
Operators per shift 5 3
Rolled first pass yield 90.3 % 92.7 %

The two operators per shift who are no longer needed in the housing stream move to the bracket family, which runs overtime. That decision was announced with the map.

Loops

Nobody can build this in one step. The method cuts the future state into loops: sections of the stream that are connected by one pull signal and can be built on their own.

The housing map has three.

Loop 1, the pacemaker loop. The cell, the finished goods supermarket and the leveling box. It contains the layout change, the machining changeover from 45 to 15 minutes and the uptime target.

Loop 2, the casting loop. Trim at the casting cell, the supermarket for trimmed castings and the signal card. It contains the casting changeover, the casting uptime and the work on porosity.

Loop 3, the supplier loop. The ingot supplier and the raw material supermarket, with delivery twice a week.

The sequence

Start with the pacemaker loop. It is closest to the customer, and it sets the rhythm that every upstream loop will have to serve. A casting supermarket built first would be sized for a cell that does not exist yet.

Then work upstream. Each new loop connects to a pull signal that already works.

Suppliers come last, when your own consumption is steady.

Each loop has a lead time it should deliver:

Loop When Lead time after
1 Pacemaker Months 1 to 3 11.5 days
2 Casting Months 4 to 6 8.0 days
3 Supplier Months 7 to 9 5.0 days

With loops and milestones, the map is ready to become a plan.