Value Stream Mapping | Part 4 of 8

Drawing the Current State Map: Material, Information, Inventory

How to draw a current state map by hand in six steps, with inventory in days and an honest picture of the information flow.

After the walk, the team has data boxes, piece counts and notes about who tells whom what to make. The current state map puts them into one picture, drawn by hand on one large sheet. If it does not fit on one sheet, the scope is too wide.

A few simple marks

A map needs only a handful of elements. Agree on a short legend of your own and use the same mark every time.

  • Customer and supplier: a box at the top right and the top left.
  • Process: a box in the bottom half, one per area in which material flows without stopping, with its data box underneath.
  • Inventory: a mark between two processes, with pieces and days.
  • Push: a plain note on the connection where a process makes what its schedule says, not what the next one needs.
  • Information: a thin line with a label. Many teams draw paper and talk as a straight line and electronic messages as a zigzag.

Six steps

1. The customer. Top right: 450 housings per day, containers of 25, one truck per day.

2. The processes. Five boxes from left to right: die casting, trim and deburr, CNC machining, wash and leak test, assembly and pack. One operator each, data box below.

3. The inventory. Between the boxes, what was counted on the walk.

4. The supplier. Top left: alloy ingots, 4.5 metric tons, once a week.

5. The information. Production control in the top center, then every line from and to it.

6. The time line. Along the bottom, covered in the next part.

Inventory in days

Pieces say little. Divide every count by the customer demand per day and inventory becomes time.

Inventory In front of Pieces Days
Alloy ingots Die casting 2,250 5.0
Castings Trim and deburr 1,350 3.0
Trimmed castings CNC machining 900 2.0
Machined housings Leak test 675 1.5
Tested housings Assembly 450 1.0
Finished housings Shipping 1,800 4.0

Raw material is counted in piece equivalents. One housing needs 2.0 kilograms of alloy, so 4.5 metric tons of ingots are 2,250 housings.

Together that is 7,425 pieces and 16.5 days. Raw material and finished goods alone hold 9.0 days, 55 percent of the total.

The information flow

Draw what happens, not what the procedure says.

In the housing stream the customer sends a 90-day forecast once a month and a call-off every day, both electronically. Production control runs its planning once a week and prints three schedules: for die casting, for machining and for assembly. Shipping gets a daily list. The ingot supplier gets a weekly order based on the forecast.

Then there is the line that is in no procedure: every morning the supervisor leaves the shortage meeting and changes priorities by talking to people. It belongs on the map.

Count the points that receive a schedule. Here there are four: three processes and shipping. Each schedule is right on Monday morning and wrong by Tuesday, because none of them knows what the next process really needs. Trim and the leak test work on whatever arrives. Material is pushed at every connection.

What the team sees

When the pencil is down, ask the team to describe the stream in a few sentences. In the example they said this:

  • We hold nine days at the two ends because we do not trust the middle.
  • Casting makes each variant once a week, so three days of castings wait for trim.
  • Four people get a schedule, and one meeting a day corrects them all.
  • A leak is found three processes and about six days after the casting was poured.

None of these sentences was new to everybody. All of them were new to somebody. The team dates and signs the map and hangs it near the stream.