A value stream map built from system data is a map of the plan. The map has to show how the plant works today, and there is only one way to find out: walk the stream with a stopwatch and count.
Rules for the walk
Walk the whole stream once first. No writing, no measuring. In the example plant the route from the shipping dock to the ingot store is 410 meters.
Then start at shipping and move upstream. The processes closest to the customer define what all others should deliver.
Measure and count yourself. Ten cycles with the stopwatch per process. Every piece of inventory counted, also the rework shelf.
One person draws, everyone collects. Split into pairs for the data, but keep one sheet and one pencil.
Announce it to every shift. The team measures the process, not the person.
The data box
Under every process box sits a small table. Seven fields are enough.
- C/T, cycle time. Seconds between two pieces leaving the process.
- P/T, processing time. Seconds one piece is actually worked on. For a single station it equals the cycle time. With parallel machines it is longer.
- C/O, changeover time. Minutes from the last good piece of one variant to the first good piece of the next.
- Uptime. Share of the planned time in which the process can run.
- First pass yield. Share of pieces that are good the first time, without rework.
- Operators. People needed per shift.
- Interval. Days until every variant has been made once.
The data boxes of the housing stream
| Process | C/O | Uptime | First pass yield | C/T |
|---|---|---|---|---|
| Die casting (shared) | 120 min | 82 % | 96 % | 55 s |
| Trim and deburr | 10 min | 100 % | 99 % | 40 s |
| CNC machining | 45 min | 90 % | 98 % | 100 s |
| Wash and leak test | 0 min | 95 % | 97 % | 50 s |
| Assembly and pack | 5 min | 100 % | 100 % | 105 s |
Machining shows why cycle time and processing time are two fields. Two machines run in parallel. Each needs 200 seconds per housing, so one housing leaves every 100 seconds. For capacity, the 100 seconds count. For the value-added time, the 200 seconds count.
Each process has one operator per shift.
Check capacity on the spot
Machining needs 450 housings times 100 seconds times two machines, which is 1,500 machine minutes per day. Two machines with 900 minutes and 90 percent uptime offer 1,620. The load is 93 percent. Only 120 machine minutes are left for changeovers and trouble.
That explains a habit. With 45 minutes per changeover, two changes a day are possible on paper. One bad hour would break the plan, so the smaller variant runs in batches of 300 every second day. The batch is the result of changeover time and free capacity.
A question at every process
Besides the numbers, ask every operator the same thing: how do you know what to make next?
In the example, die casting, machining and assembly each get a weekly schedule. Trim and the leak test work on whatever arrives. Every morning the supervisor comes back from the shortage meeting with changes. These answers become the information flow on the map.
What five people do
One more number comes out of the walk. Add the manual work per housing: 10 seconds of checking at the casting cell, 40 at trim, 25 for loading the machines, 50 at the leak test, 105 in assembly. That is 230 seconds. At a takt time of 120 seconds, 230 seconds are work for two people. The stream employs five per shift.
Nobody is idle. The processes stand 85 meters apart, so each operator is tied to one island. No single department can see this.