Takt Time
The pace of customer demand: the available working time divided by the number of units the customer needs in that time.
Formula
Takt time = Available working time / Customer demand
Worked examples
- 01Assembly line with two shifts of 7.5 hours of working time: 54,000 seconds available, customer demand 900 units per day. Takt time = 54,000 / 900 = 60.0 seconds.
- 02Cell on one shift of 7.25 hours: 26,100 seconds available, customer demand 290 units per day. Takt time = 26,100 / 290 = 90.0 seconds.
- 03Final packaging, 3 shifts of 7.5 hours: 81,000 seconds available, customer demand 2,430 units per day. Takt time = 81,000 / 2,430 = 33.3 seconds.
- 04Check against cycle time: at a takt of 60 seconds, a station with a cycle time of 66 seconds cannot keep pace. The gap of 6 seconds per unit costs 90 minutes per day at 900 units.
Pitfalls
- Takt is a demand number, not a machine number. Do not confuse it with cycle time.
- Subtracting planned stops twice, once in available time and once in a lower OEE, sets the takt too short.