A pump plant buys production material for EUR 118 million a year from 340 active suppliers. Purchasing knows every one of them by name. Nobody can say which ten matter most.
Supplier management starts with a simple fact: you cannot manage 340 suppliers equally. Put the effort where the value and the risk are.
Start with the spend
Export twelve months of purchase volume by supplier and category, sort it, and add a cumulative share. The picture is almost always the same. In the example, 45 suppliers carry 80 percent of the volume, and 190 suppliers together carry less than 5 percent.
That one sorted list already changes the work. The 45 deserve scorecards, reviews and attention. The 190 deserve a catalog, a framework order and as few transactions as possible.
Add supply risk
Spend alone is not enough. A mechanical seal worth EUR 40,000 a year can stop a line that produces EUR 200,000 a day. Score supply risk from 1 to 5 with facts, not feelings:
- number of approved sources for the part,
- lead time and how long a new source would take to qualify,
- technical complexity and tooling,
- the market situation for the material or process.
Four segments
With value and risk you get four segments, each with its own rules:
- Strategic, high value and high risk: partnership, quarterly reviews, joint development.
- Bottleneck, low value and high risk: secure supply with stock, a second source or longer agreements.
- Leverage, high value and low risk: competition, bundling, should-cost models.
- Routine, low value and low risk: simplify with catalogs and framework orders.
Segment per supplier and category. A supplier can be strategic for castings and routine for packaging.
One page per category
For the largest categories, write the strategy on one page: volume and suppliers, the market, the target in three years, the sourcing model, the actions this year and the owners.
For castings in the example: EUR 14.2 million with four suppliers, one of them holding 62 percent. The target is two qualified sources for every housing family, below 150 ppm and 98 percent on-time delivery within three years. This year: develop the main supplier, qualify a second source for one housing family, build a should-cost model.
Agree it across departments
Purchasing, quality, logistics and engineering each see a different supply base. Purchasing sees price, quality sees defects, logistics sees delays, engineering sees technology. The segmentation is the first place where all four views meet.
Agree it together once a year. Every later decision, from the scorecard to the risk list, builds on it.