Three offers arrive for a new machined part. Supplier B is 12 percent cheaper. Two years later the part has a history of late deliveries, a failed capability study and a second tool paid by you.
When nothing else is agreed, price decides by default. A weighted selection matrix makes the other criteria count.
Agree the criteria first
The selection team, purchasing, quality, logistics and engineering, agrees the criteria and their weights before the offers are opened. A typical set for production parts:
- quality capability and quality system, 25 percent,
- delivery capability and capacity, 20 percent,
- total cost of ownership, 25 percent,
- technical capability, 15 percent,
- risk and financial stability, 15 percent.
The order matters less than the timing. Weights set after the offers are known tend to follow the preferred supplier.
Score from 1 to 5 with evidence
Each criterion gets a score from 1 to 5 per supplier, based on what the team has seen: the self-assessment, the visit, the quotation details, references and, for critical parts, a process audit.
| Criterion | Weight | A | B | C |
|---|---|---|---|---|
| Quality capability | 25 | 4 | 3 | 4 |
| Delivery and capacity | 20 | 3 | 4 | 4 |
| Total cost of ownership | 25 | 3 | 5 | 3 |
| Technical capability | 15 | 4 | 2 | 4 |
| Risk and stability | 15 | 4 | 2 | 3 |
| Weighted score | 3.55 | 3.40 | 3.60 |
Supplier B has the best cost but the weakest technology and the highest risk. Supplier C wins on balance.
Six selection steps
- Request for information to a long list of five to eight suppliers.
- Self-assessment and a first visit for the short list.
- Request for quotation with complete, released drawings and specifications.
- Evaluation with the matrix and a total cost comparison.
- Process audit at the preferred supplier for critical parts.
- Decision recorded with reasons, nomination with conditions.
Step 3 deserves special care. Quotations based on preliminary drawings produce prices that change with every revision, and every change becomes a negotiation.
Nominate with conditions
A nomination can carry conditions: a capability study before series, an open point from the audit closed by a date, a second shift ready before the volume ramps up. Write them into the nomination letter and track them like actions.
Record the reasons
Keep the matrix, the total cost comparison and a short text with the reasons for the decision. When the part causes problems two years later, the record shows whether the risk was known and accepted or overlooked.
It also protects good decisions. A buyer who chose the more expensive supplier for documented reasons should not have to defend that choice from memory.