Most supplier problems of the next five years are created in the twelve months before start of production. A tolerance nobody questioned, a tool that was never run at full speed, a capability study that was promised for later.
A structured launch of new parts costs time before series. It saves much more time after.
Six steps to approval
- Feasibility: the supplier confirms drawing, tolerances, capacity and timing in writing, with open points listed.
- Process plan: process flow, a risk analysis of the process, a control plan. Reviewed by your supplier quality engineer.
- Initial samples: parts from series tools and the series process, measured in full against the drawing.
- Capability: a capability study for critical characteristics. A Cpk of 1.33 or more, or a 100 percent check until it is reached.
- Run at rate: production at series speed over a defined time at the supplier, to prove output and quality together.
- Part approval: all documents complete, approval signed by quality, series orders released.
Each step has an owner and a date in the launch plan of the part. A part that misses a step is visible weeks before start of production, not on the day.
Ask early, ask in writing
The feasibility step is the cheapest moment to change anything. A tolerance of 0.02 mm that could be 0.05 mm, a material that is hard to source, a surface treatment only one supplier can do. Ask the supplier to name these points in writing, and let engineering answer them.
Run at rate is not optional
Initial samples show that the supplier can make good parts. A run at rate shows that it can make enough good parts at series speed, with series staff, on series equipment. Many launch problems only appear at full speed: tool temperature, operator workload, material handling.
The safe launch period
For the first 90 days after start of production, critical new parts get an extra check at the supplier and at your incoming inspection. The extra check ends with data, for example 30 days without a defect, not with a date in the calendar.
Changes after approval
An approved part stays approved only while the process stays the same. Agree that the supplier informs you before it changes material or sub-supplier, tools, the production site or the process sequence. You decide whether new samples are needed.
Unannounced changes are one of the most common causes of sudden quality problems with parts that ran well for years. The rule costs nothing to agree and a lot to forget.
One list for all launches
Keep all new parts in one list with their launch steps, the planned start of production and a status. Parts with less than 30 days to go and open steps are at risk and belong in the weekly meeting.