Supplier Management | Part 8 of 10

Develop Suppliers With Lean Methods

Pressure moves problems, development removes them. How to choose the suppliers worth developing and work with them on site.

The standard answer to a weak supplier is pressure: escalation letters, penalty threats, a tender for the next part. For leverage parts with many alternatives this can work. For strategic parts it usually moves the problem around.

Supplier development takes the other route. You go to the supplier with people and methods, and you fix the process together.

Choose where it pays

Development costs time, typically two to five days per month of a supplier quality engineer over six months. It pays where three things come together:

  • the supplier is strategic or a bottleneck, so switching is slow or risky,
  • the gap is large and measurable, in ppm, delivery or cost,
  • the supplier’s management is willing to work on its own process.

In the pump plant example, the housing casting supplier scored 35.5 points, class C, with 820 ppm and 88 percent on-time in-full. A new source would need six months and a new tool. Development was the faster path.

Five methods that work at suppliers

  • Value stream mapping from raw material to your dock makes lead time, stock and the bottleneck visible.
  • Standard work and process control for the critical steps reduce variation.
  • Setup reduction on molds and fixtures allows smaller batches and shorter lead times.
  • Planned maintenance by shot count or hours prevents wear from turning into defects.
  • Daily problem solving at the line finds causes while the evidence is fresh.

These are the same methods that work in your own plant. Use the same language and the same tools, and the supplier team learns them as part of its own system.

A development plan with numbers

The plan for the casting supplier set three targets for six months: quality from 820 to 260 ppm, delivery from 88 to 96 percent, the total score from 35.5 to 74.5. The main actions were mold maintenance by shot count, sampling of the area with porosity, a capability study for the sealing surface and a frozen schedule of two weeks from the plant.

With 260 ppm the quality points rise from 40 to 70, with 96 percent the delivery points from 0 to 80. Together with a better collaboration rating, the supplier reaches class B.

Fix your own side too

Half of the late deliveries in the example started with schedule changes by the plant itself. A development plan that only asks the supplier to change is not a partnership. Write your own actions into the plan as well.

Share the gains

Agree before you start how savings from joint improvement are shared. A common rule is half and half for a defined period. Suppliers who keep nothing of the gain will stop bringing ideas, and the next improvement will again need pressure.

Recognize progress

When a supplier moves from class C to B, say so in the review and in writing. Recognition costs nothing and tells the supplier team that the work was seen.