A risk you know and have prepared for is a plan. A risk you discover during the disruption is a crisis. The difference between the two is usually a list that someone made before it was needed.
Start with the parts, not the suppliers
Do not begin with a complete risk model of 340 suppliers. Begin with one question: which parts would stop our line within two weeks if one supplier failed?
For each of these parts, score two numbers from 1 to 5:
- Impact: 5 means the line stops within two weeks and no alternative exists.
- Probability: based on quality history, capacity, financial signals, region and sub-suppliers.
The score is impact times probability. 12 or more needs a written mitigation with an owner. 20 or more needs a decision by management.
A worked risk list
In the pump plant example:
- housing casting, single source in practice: 5 × 4 = 20,
- motor 4 kW, single source: 5 × 2 = 10,
- control board, two sources but components at end of life: 4 × 3 = 12,
- mechanical seal, single source: 4 × 3 = 12.
Management decided on the castings: a second source for one housing family within nine months and four weeks of safety stock until then.
Five risk types and their signals
- Single source failure: quality problems, capacity complaints, key people leaving.
- Financial distress: requests for faster payment, delayed investments, changes in ratings.
- Capacity limit: rising lead times, partial deliveries, overtime at the supplier.
- Regional disruption: weather, energy shortages, transport problems, conflicts.
- Sub-supplier failure: your supplier cannot name its own sources.
Agree who watches which signal. For critical parts, map the tier 2 suppliers and ask to be informed of changes.
Responses
- Second source, qualified or at least prepared with samples.
- Safety stock that matches the time to react.
- Tool ownership and access, so a tool can move if needed.
- Agreements on capacity and notification of changes.
- Design alternatives, for example a second component that fits the same board.
The cost of resilience
Resilience is not free. Four weeks of safety stock for the castings bind about EUR 100,000 of capital. A line stop of two days costs more. Make the trade-off with numbers, decide it consciously, and review it when the risk changes.
Review monthly
Keep the list short and alive. Each month the category managers review the top risks: what moved, is the mitigation working, is a new risk visible? A risk list that changes every month is being used. One that never changes is being filed.