Six Key Figures That Keep Times and Capacity Honest

Coverage, age, plan against actual, utilization, bottleneck load and productivity, and why an outlier is a finding about the time before it is one about the team.

A measured plant stays measured through routines, not through a project. Six numbers, one monthly review and one audit every six months are enough.

The six

Key figure How it is calculated M2 start
Routing coverage Operations with a measured time divided by all operations 65 %
Age of the times Share of standard times older than 36 months 26 %
Time coverage Standard hours earned divided by hours booked 80.0 %
Utilization factor Net productive share of the planned operating time 80 %
Bottleneck load Load of the highest loaded station against the program 105.5 %
Area productivity Units produced per hour booked 3.40

The first two are counted once a month from the operation list and need no system. The next two come from the booking data and the sampling study, the last two from the capacity calculation and the output.

Plan against actual, read correctly

Time coverage per station is the figure that finds wrong times faster than anything else. Standard hours earned divided by hours booked, for the same program and the same people.

With the old times, the six stations of area M2 spread from 70.5 to 103.1 percent on a program of 44,000 units. The test bench looked like a 70 percent station and the assembly station looked like a star, and for two years the conversation was about performance.

With the measured times and the same booked hours, the spread fell to 78.5 to 84.8 percent. Nothing about the people changed. The twenty points that remain below 100 are exactly the twenty points of measured loss from the work sampling study: six points of handling above the allowance, nine of searching and waiting, five of rework.

That is the rule to write down and repeat: an outlier in time coverage is a finding about the standard time, the method version and the booking before it is one about the team. Check those three first.

Coverage and age need owners

Coverage without a plan is a number that never moves. Area M2 went from 65 to 95 percent in twelve months in five named steps, each with an owner: the pilot stations and the machine-paced cycles first, then the compared variants, then the second product group, then the low volume remainder.

Age is the figure that decays on its own. Twenty-six percent of the times were past thirty-six months at the start. The fix is not a campaign but a line on the change record: a change to the method is not closed until the time has been reviewed.

Four routines

A monthly coverage and age report by the industrial engineer, listing times due for review and any difference between register and routings.

A monthly plan against actual review by the area manager with the team, reading coverage per station and treating an outlier as a question about the time.

A capacity comparison by the planner every quarter and at every program change, with the load per station, the bottleneck and the scenarios.

An audit with the twenty-five statements every six months, ending in one action with an owner and a date.

What it is worth

The measurement in area M2 took about 56 hours of internal work, roughly EUR 3,640. Against that: a capacity gap of 2,715 units closed, worth EUR 114,030 of contribution margin, and 899 attendance hours released by lifting the utilization factor from 80 to 85 percent, worth EUR 52,115. The investment of EUR 41,000 paid back in 3.0 months, and the EUR 95,000 request for the wrong station was withdrawn and reported as avoided spending rather than booked as a saving.

The hours this work produces feed four other decisions: head count and shift models, the production program and its sequence, the standard work sheet and the takt, and the rates in costing. Measure once here and all four get the same number.