The Standard Time Register: Validity, Review, Routings

The fields a standard time needs, the rules that keep it current, and how the register and the routing in the planning system stay in step.

Times decay. Not because anyone changes them, but because the work around them changes: a new fixture, a different seal kit, a rebuilt station, a lot size cut in half. Without one list, one owner and one release step, the times of a plant live in spreadsheets on six computers and nobody knows which version the planning system is actually using.

What the register holds

A row per operation, with everything a later reader needs to judge the number.

The operation and product group link the row to the routing. The standard time appears with its parts visible: observed time, rating, basic time, allowance, machine time, setup time and lot size. The source says where it came from, and the method version names the fixture, tool and work instruction it belongs to. Measured by and measured on make an audit possible. The spread and the precision reached let a user judge how firm the number is. Valid from and review date say when it entered planning and when it must be looked at again. And the status is one of valid, provisional, to review or retired.

Five rules that keep it current

Every time gets a review date: thirty-six months for a measured time, twelve months for a provisional time or an estimate.

A trigger forces a review earlier: a change of method, fixture, tool, material, layout or quality requirement, or a program change above 20 percent.

Provisional is visible. A provisional time is marked in the register and in every report that uses it, so nobody builds a quotation on one by accident.

One release step. A time enters planning when the area manager and the industrial engineer have signed it, not when somebody finishes a spreadsheet.

Nothing is overwritten. A change creates a new row with a new valid-from date, and the old row is set to retired and kept.

The rule that prevents the most trouble is the simplest: a change to the method is not finished until the time has been reviewed. Put that review on the change record itself, with an owner, and the register stays current without a campaign.

The register and the planning system

The register is the source. The routing in the system is a copy. Problems start when the copy becomes the source, which happens the first time a planner edits a time during a shift to make a schedule work.

Six questions settle it, and the answers are independent of which software you run. One named person may change a time in the system, and only on the basis of a released register row. Changes reach the system in a weekly transfer with a list of changed operations, checked afterwards. A monthly comparison of register and routing finds differences, and a difference is a finding to report, not something to correct quietly. Setup time and lot size are carried as their own fields rather than folded into the time per unit. Machine time and manual time stay in separate fields, so capacity for people and for equipment can be calculated apart. And coverage, age and the number of differences are reported every month with the area key figures.

Coverage is a plan, not a wish

Of the 148 operations in the M2 product group, 96 carried a measured time at the start, which is 65 percent, and 38 of those were already past thirty-six months.

Month What was measured Coverage after
0 Starting point of the product group 65 %
3 Pilot stations and all machine-paced cycles 74 %
6 The 28 compared variants measured 86 %
9 High volume operations of the second group 92 %
12 Remaining low volume operations 95 %

Twelve months, five steps, one owner per step. The last seven operations stayed provisional on purpose: they are new variants whose method is not yet stable, and saying so is more useful than filling the field.