A stopwatch answers how long one operation takes. It cannot answer where a day goes. For work that is varied, interrupted or spread over a large area, many short looks at random moments tell you more than continuous timing ever will.
How the method works
You define the categories first, observe at random times, and count. The share of observations in a category estimates the share of time spent in it, and the precision of that estimate follows from the number of observations. There is no rating, the effort is small, and it is the fastest honest way to the utilization factor that every capacity calculation needs.
Size the sample before the first round
Four questions decide the size. What share are you most interested in, how precise does it have to be, how many observations does that need, and how will you reach them.
The arithmetic is four times the expected share times one minus the expected share, divided by the square of the precision written as a decimal. In area M2 the expected share of productive assembly work was around 60 percent and the precision wanted was plus or minus 3 percentage points at 95 percent confidence. Four times 0.60 times 0.40 divided by 0.03 squared gives 1,067 observations.
That was reached with twenty rounds a day, six stations per round and ten working days: 1,200 observations, which gave a precision of plus or minus 2.8 percentage points. A rough guess for the expected share is good enough, because it only sizes the sample.
Rules for the rounds
Draw the round times from a list before the day starts. A round every hour on the hour measures the hour, not the day.
Record what you see at the moment you arrive, not what happened before or after. Walk the same route and use the same categories every time, and invent no new category during the study. And announce it: people must know what is being counted. A study done quietly is worth nothing, whatever the numbers say.
The result and what it means
| Category | Covered by | Share |
|---|---|---|
| Assembly work on the order | The basic time | 61 % |
| Setup and changeover | The setup share | 6 % |
| Material handling and fetching | 5 points by the delay allowance | 11 % |
| Searching and waiting | Nothing | 9 % |
| Rework and problem solving | Nothing | 5 % |
| Personal time outside break times | The rest allowance | 8 % |
Read the third column against the second. Sixty-one points of assembly work and six points of setup are already inside the standard time. Eight points of personal time are covered by the eight percent rest allowance, and five of the eleven handling points by the five percent delay allowance.
What remains uncovered is six points of handling, nine points of searching and waiting and five points of rework: twenty points in total. The utilization factor of area M2 is therefore 80 percent, and every point of the missing twenty has an address.
Why this matters more than it looks
Most capacity calculations use a utilization factor that came from a handbook or from last year. That single number decides whether a plant believes it has enough capacity, and it is usually wrong in the optimistic direction.
A ten-day sampling study costs about two hours a day of one person and replaces that guess with a measured figure. In area M2 it turned 900 planned minutes per station per day into 720 net minutes, and 720 net minutes is what the bottleneck analysis and the investment decision were built on.
It also hands you the improvement list for free. Nine points of searching and waiting and five points of rework are not allowance and never will be. They are work to remove, and lifting the factor from 80 to 85 percent released 899 attendance hours a year, worth EUR 52,115 at the area rate.