Workforce Planning and Shift Scheduling | Part 1 of 8

Workforce Requirement: From the Production Program to Attendance Hours

How to turn units and work content into the hours a production area has to staff, and why a measured utilization decides the result.

Ask a production manager how many people an area needs and the answer usually starts with how many it has. Head count that comes from history survives every program change, and the cost shows up elsewhere: overtime, agency hours, late deliveries. The alternative is a calculation anybody in the room can follow.

The example of this series

A plant for electric drive units runs assembly area A2: eight stations, two shifts of 7.5 paid hours, 250 operating days. Next year the program grows by 17 percent. The area has 21 employees, and nobody can say whether that is the right number.

Units times work content

The requirement starts with the program and the work content per unit:

Product family Work content per unit (min) Units per year Productive hours
D1 Standard drive 6.0 138,000 13,800
D2 Geared drive 9.0 78,000 11,700
D3 Special drive 15.0 24,000 6,000
Total 240,000 31,500

Productive hours are units times work content divided by 60. The work content is the content of the whole product across all eight stations, at 100 percent performance, including the allowances of your own time standards. Station times are needed for line balancing. For staffing you need the sum.

A usable work content is dated, has a source, includes your own allowances rather than a figure borrowed from another plant, is reviewed when the product or the process changes, and covers the variants at least as a weighted average. Where the figures come from is a subject of its own: time study, predetermined time systems and work sampling belong to work measurement. For staffing, treat the quality of the work content as a named risk rather than an assumption.

Utilization turns productive hours into attendance hours

Nobody produces standard output for every paid minute. Utilization is the share of paid attendance time at the station that turns into standard output. Measured over twelve weeks in area A2, it is 90 percent, and the missing ten points have an address:

Loss What reduces it Share of attendance time
Shift start, handover, shift end A handover standard and a staffing board filled in before the shift 3.1 %
Waiting for material or a part Supply in the rhythm of the line 2.4 %
Short stops and small faults Autonomous maintenance, first-level problem solving 1.8 %
Rework at the station Quality at the source, test earlier in the sequence 1.5 %
Daily meeting, instructions, area tasks Nothing. Plan it as time instead of losing it as a surprise 1.2 %

Attendance hours are productive hours divided by utilization: 31,500 / 0.90 = 35,000 hours per year, or 140 hours per operating day. At 7.5 paid hours that is 18.7 posts, which the shift model will turn into whole posts.

Measure utilization, do not assume it

A utilization taken from a handbook moves the whole calculation. One percentage point in area A2 is about 390 attendance hours per year, a quarter of an employee. Five points are more than one employee, and they are usually cheaper to win than to hire.

Measuring it needs no project. For three weeks, on both shifts, record paid attendance hours at the stations and standard hours produced, which is good units times work content. Utilization is the second divided by the first. Twenty shifts give a first figure, sixty give one you can plan with.

What the number is and is not

Thirty-five thousand attendance hours is a statement about the program, not yet about people. It says nothing about vacation, absence, shift models or qualification. It is the one figure every later argument comes back to, so agree it first and write it down with its date, its work content source and its measured utilization.