Introducing a New Process: Pilot, Training and Cutover

How to test a target process with real cases, train the roles and switch over on a fixed date without losing the cases in progress.

A target process on paper is a guess. It becomes a process when real cases run through it. The way from the wall to daily work has three stages: pilot, training and cutover.

The pilot

A pilot runs the complete target process on a limited part of the business. Six points define it.

  • Extent. One team, one region or one product group, and all cases of that extent.
  • Duration. Long enough for 100 cases or more, with a fixed end.
  • Rules. All rules of the target process apply, in writing.
  • Systems. Use what exists. Simple aids replace later automation.
  • Measurement. The same six numbers as in the baseline, every week.
  • Decision. Criteria for go, adjust or stop are set before the start.

The valve plant of this series piloted its new order processing in the sales region North, with one order team of four people, for eight weeks and 264 orders. The conversion of the quote into the order, later a function of the ERP system, was replaced by a shared list. The criteria were a lead time below 7 days and a first pass rate above 75 percent.

What the pilot showed

Key figure Baseline Target Pilot
Office lead time, working days 15.7 5.2 5.9
First pass rate 58 % 84 % 81 %
Queries per 100 orders 60 20 24
Touch time per order, minutes 230 140 152

Both criteria were met. Just as important were three corrections of the design. The daily quote cell moved from 08:00 to 10:30, after the inquiries of the morning had arrived. The inquiry checklist lost one field that customers could never answer and gained a free text field for the application. And the standard lead times needed a second value for valves with special actuators.

Training

Train by role and with real cases. Two hours per role on its own steps, and one hour for everybody on the whole path, the key figures and the review. In the example that added up to 150 hours for 48 people from the order teams, application engineering, finance, planning, shipping and the sales field staff.

Each workplace gets three aids: the drawing of the process, the rules on one page and the checklist for its own step. How to write a good instruction for a single step is the subject of the series on work instructions.

The cutover

The switch from the old to the new process is a date, not a period. Announce it four weeks ahead and prepare four things.

  1. Cases in progress. A written rule decides. In the example: quotes sent before the date finish in the old process, every new inquiry starts in the new one.
  2. Old tools. Private spreadsheets, old forms and mail folders are closed on the cutover date. As long as the old path exists, some cases will take it.
  3. Support. The pilot team sits with the other teams during the first two weeks.
  4. Daily look. A short daily meeting at the board of each team, with yesterday’s cases that fell out of the standard path.

Expect a slow start

The numbers do not jump to the target on the first day. In the valve plant, the plant-wide lead time went from 12.1 days to 9.0 and then to 7.2 in the month of the cutover. It reached 5.2 days four months later, after the changes in the ERP system were live.

Measure every week during this time and collect every case that fell back into the old path. Most of them point to a rule that is not clear enough, and a few point to a rule that is wrong.

When the process runs everywhere, the next question arrives: which parts of it should software take over? That is the subject of the next part.