A drawn and measured process contains its own diagnosis. Seven patterns explain almost all lost time in business processes, and each one can be marked on the drawing with a colored note.
Seven patterns
- Loop. An arrow goes back. Ask what was missing the first time and who could have known.
- Handoff. An arrow crosses a lane. Ask what the next role needs and whether it gets it complete.
- Media break. Two neighboring steps use different systems. Ask why the data is not taken over.
- Double work. Two steps deal with the same object. Ask what the second check finds that the first did not.
- Approval level. A step only says yes or no. Ask how often the answer is no.
- Sequence. Steps follow each other without needing each other. Ask whether both could start at once.
- Batch. Work is collected and done at fixed times. Ask what it would cost to do it per case.
The list of the example
In the order processing of the valve plant, the workshop team found eight weak points.
| Weak point | Pattern | Days per order |
|---|---|---|
| Clarification and price in two departments and two spreadsheets | Handoff | 2.0 |
| Credit check and delivery date one after the other | Sequence | 2.0 |
| Invoices created twice a week and checked by a second person | Batch | 1.8 |
| Two approval levels for every quote | Approval | 1.3 |
| Technical check done twice, at quote and at order | Double work | 1.2 |
| Inquiry accepted without the required data | Loop | 0.8 |
| Order retyped from the quote by a second department | Media break | 0.7 |
| Confirmation and shipping documents typed by hand | Media break | 0.5 |
Together they cost 10.3 days and 95 minutes per order. The whole office lead time is 15.7 days. Eight points explain two thirds of it.
Rate the effect per case
Every weak point gets two numbers: the minutes of work and the days of waiting it costs per case, as an average over all cases.
Multiply by the cases per year and the list becomes a ranking. The first weak point of the table costs 15 minutes on 4,800 orders: 1,200 hours per year, and the largest single block of waiting.
Rate the effort
Then add the kind of effort it takes to remove the weak point.
- Rule change. Management decides, and it applies from Monday. Approval limits, required fields, who checks what.
- Organization change. Tasks move between roles or teams. Needs agreement and some weeks.
- System change. Software must be adapted. Needs a budget and months.
Sort by effect, then start with the rule changes. In the example, four of the eight weak points were rules: the approval levels, the second technical check, the serial order of credit check and delivery date, and the acceptance of incomplete inquiries. Together they cost 45 minutes and 5.3 days per order, and removing them cost a decision.
The approval question
Approval levels deserve their own look, because they feel like control. The test is simple: how often does the approver say no?
In the valve plant, the second approval level had rejected 3 of the last 400 quotes. All three were large quotes with high discounts. A check that finds something in fewer than one case in a hundred is a habit. It can be replaced by a rule: approval only above EUR 50,000 or above 10 percent discount, which is one quote in five.
What not to do
Do not look for solutions while you collect weak points. Collect, count and rate first. The method of working through office waste one by one is described in the Lean Administration module. Here the list has one purpose: it is the input for the target process, which is the subject of the next part.