Factory Layout Planning | Part 8 of 8

The Move and Implementation Plan

How to move a running production into a new layout in phases, with empty targets, secured output and a ramp-up curve.

A layout exists when the machines stand in it. The move plan answers three questions: in which order things move, what secures the output, and when the project is finished.

Phases instead of one big weekend

The pump plant of this series moves 28 machines and 10 assembly stations into its new U-shaped layout in twelve weeks:

Phase Weeks What happens Machines
Prepare 1 to 4 Utilities laid in the target cells, stock built, buffers cleared 0
Phase 1 5 Testing moves next to shipping 3
Phase 2 6 to 8 Grinding, washing, turning and sawing move on three weekends 17
Phase 3 9 to 10 Shutdown: machining centers and assembly swap sides 8
Ramp-up 11 to 12 Output at 70 and 90 percent, open points closed 0

Every move needs an empty target

In a full hall, areas block each other. Turning has to go where grinding stands, grinding where washing stands, and washing where turning stands. Nobody can go first.

The chain is broken with free space. In the pump plant it comes from two sources: the buffer areas, which are cleared from 500 to 100 square meters in the preparation, and the two cells that testing leaves in phase 1.

Phase 2 then reads like a sliding puzzle. One grinder moves into a cell that testing left, a lathe takes the place of the grinder, washing follows, and so on, seven steps in total.

Every row of the move plan has a column that says why the target is empty. A row without an answer blocks everything behind it.

The swap

Phase 3 is the hardest. Machining centers and assembly have to change sides, eight heavy machines against ten stations. Two machining centers move into the cells turning left behind. Assembly stations follow into the cells of these two machines and free the space for the next pair. After four rounds everything stands where the layout wants it, and two new assembly stations are added.

The plant uses its two-week shutdown for this phase.

Before each machine moves

  • Target position marked on the floor, foundation and floor load checked.
  • Power, air, coolant and data ready at the target and tested.
  • Stock of the parts the machine makes covers the planned downtime plus two days.
  • Checks after the move defined, with the person who releases the machine.

Securing the output

Customers do not care about the layout. The plan therefore contains a ramp-up curve and the stock that covers it.

Week Output Units short
11 70 percent of 500 units 150
12 90 percent of 500 units 50
13 100 percent 0

The plant expects to be 200 units short and builds 300 units of stock in the first four weeks. The remaining 100 units are the reserve for a machine that fails its first capability check.

While the move runs

One move manager decides on the floor. A daily stand-up at the plan shows what is moved, tested, released and blocked. Nobody takes shortcuts on isolation of energy, lifting and floor loads.

Finished means measured

The project does not end when the last machine is bolted down. It ends when the goals of the planning brief are measured in the new layout.

Eight weeks after the release, the pump plant counts the transports of one week again and repeats the calculation. The plan promised 7,980 instead of 14,100 meters per day, 31 instead of 54 meters per transport, 1,000 square meters for assembly and 200 in reserve. The plan is a forecast, and the count is the result.

After that the layout gets an owner, and no machine or rack is added without a look at the from-to matrix and the space balance.