Factory Layout Planning | Part 6 of 8

Evaluating Layout Variants: Utility Analysis, Transport Effort and Investment

How to compare layout variants with weighted criteria, transport effort and investment, and why a layout rarely pays by transport alone.

One layout proposal is an opinion. Three proposals with the same numbers are a decision. The evaluation has three views: transport effort, a utility analysis and money.

Three variants

The pump plant of this series compares three ways to change its hall of 4,800 square meters:

Variant What changes Meters per day Investment in EUR
A Minimal Only testing moves next to shipping 11,270 50,000
B U-flow All areas move except receiving, painting, shipping 7,980 310,000
C Ideal As B, and the paint shop moves 10 m west 7,250 730,000

Today the hall has 14,100 meters per day. Variant A cuts that by 20 percent, B by 43 percent, C by 49 percent.

Variant A has a flaw: assembly stays at 800 square meters, so the extension would still be needed.

The utility analysis

A utility analysis scores each variant against weighted criteria. Six criteria with weights that add up to 100, scores from 1 to 5:

Criterion Weight A B C
Material flow 30 2 4 5
Space for assembly and reserve 20 1 5 5
Flexibility and expansion 15 2 4 4
Safety and work environment 15 3 4 4
Implementation risk and downtime 10 5 3 1
Transparency and supervision 10 2 4 4
Weighted score out of 500 100 225 410 420

Variant B: 30 x 4 + 20 x 5 + 15 x 4 + 15 x 4 + 10 x 3 + 10 x 4 = 410. The layout of today scores 180.

Rules for an honest score

  • Weights first. Criteria and weights are agreed before the variants are shown.
  • No money inside. Investment and savings are compared separately.
  • Score by rule. Where a number exists, the number sets the score. For material flow: above 13,000 meters per day a 1, below 7,500 a 5.
  • Test the result. Change the heaviest weights and see whether the ranking holds.

With material flow at 20 and implementation risk at 20, variant B scores 400 and variant C 380. When two variants are this close in utility, money and risk decide.

The investment

Variant B costs EUR 310,000. Moving and recommissioning 28 machines takes EUR 140,000, utilities EUR 75,000, and the rest goes to floor, stations, planning and contingency.

The benefit per year

The shorter ways save 153 minutes of forklift travel per day, 612 hours per year, EUR 30,600 at EUR 50 per hour. Buffers shrink from 500 to 100 square meters, and EUR 150,000 less stock saves EUR 30,000 of carrying cost at 20 percent. Together that is EUR 60,600 per year.

Against this benefit alone, variant B pays back in 5.1 years.

The real comparison

It is the wrong comparison. Assembly needs its 200 square meters either way. The alternative to variant B is not doing nothing. It is the extension.

Item Extension Variant B Variant C
Benefit per year in EUR 0 60,600 64,250
Time to completion in weeks 39 12 16
One-time cost in EUR 480,000 310,000 730,000

Variant B costs EUR 170,000 less than the extension, is finished in 12 weeks instead of nine months and makes the flow shorter instead of longer. Variant C buys 10 more points and EUR 3,650 more benefit per year for EUR 420,000 of additional investment.

The plant decides for B.

The pattern behind the example

A layout rarely pays by transport alone. It pays by what it makes unnecessary: a building, an external warehouse, stock.