When a hall is full, the first idea is to build. The space balance asks first how many square meters each area really needs. In grown halls the answer is often that space is not missing. It is in the wrong place.
Four layers of space
The requirement of an area is built from four layers:
- Footprint. The machine or station itself, with cabinets and chip conveyors. Measured, not taken from the catalog.
- Operating and maintenance. Where the operator stands, where doors open, where a spindle is taken out for repair. Often as large as the footprint.
- Material. Staging places for incoming and outgoing loads, tools and fixtures.
- Aisles. The share of main and side aisles that serves the area.
The first three layers add up to the net area. A common planning value for the aisles is 20 percent of the gross area, so that gross area = net area x 1.25.
Worked example
The pump plant of this series has eight machining centers. Each needs 30 square meters of footprint, 30 for operating and maintenance and 20 for material.
| Area | Calculation | Square meters gross |
|---|---|---|
| Machining centers | 8 x 80 = 640 net, x 1.25 | 800 |
| Turning | 8 x 60 = 480 net, x 1.25 | 600 |
| Assembly today | 10 stations x 50 + 80 + 60 = 640 net, x 1.25 | 800 |
| Assembly required | 12 stations x 50 + 80 + 120 = 800 net, x 1.25 | 1,000 |
Two more stations and a larger kitting area are the 200 square meters behind the request for an extension.
Sizing a staging area
Material space is where estimates go wrong, so calculate it:
Staging places = loads consumed per hour x supply interval in hours, rounded up, plus one.
A machining center for housings works 25 housings in the 15 hours of two shifts. With 4 housings per pallet it uses 0.42 pallets per hour. With a supply every 2 hours the result is 0.83, rounded up to 1, plus 1: two places for incoming pallets and two for outgoing ones.
Buffers are calculated, not inherited
A buffer between two processes covers the difference in their rhythm. It is sized in loads, converted into square meters and marked on the floor.
In a grown hall, buffers have a second cause: distance. When the next process is 80 meters away, nobody drives for one bin. The pump plant holds 500 square meters of such buffer areas, spread over five corners of the hall. With consecutive processes side by side, the plan keeps 100 square meters next to grinding for parts that wait for the paint batch.
The balance
| Area | Today | Required |
|---|---|---|
| Nine areas without change | 3,500 | 3,500 |
| Assembly | 800 | 1,000 |
| Buffer areas | 500 | 100 |
| Total | 4,800 | 4,600 |
All values are square meters. The hall is full today and still has 200 square meters more than it needs.
Reading the result
- Required below available. Space is enough and the problem is arrangement. This is the pump plant: 4,600 of 4,800 square meters.
- Required equals available. No reserve. Reduce buffers and storage first, then look at racks and mezzanines for light areas.
- Required above available. Space is really short, after all buffers were sized by calculation. Only now are an extension, a second shift or outsourcing the right questions.
The reserve is a goal
A layout without reserve is full on the day it starts. Plan 5 to 10 percent of the area as one connected block, next to the area that will grow or at an outer wall. The pump plant keeps 200 square meters, two cells of the grid, beside assembly.
The question is no longer where to build, but how to arrange 46 cells in a hall of 48.