A layout project usually starts with a drawing. Somebody moves a few rectangles on the plan of the hall, somebody else objects, and after three meetings the layout that wins is the one of the department that argued best. Systematic layout planning starts somewhere else: with goals that carry numbers and with data about what flows through the hall.
The example in this series
A plant builds pump units for industrial applications: 160 employees, 24,000 units per year, 100 units per day. The hall measures 80 m by 60 m, 4,800 square meters, and has grown by process over 20 years. Ten areas share it, from receiving through sawing, turning, machining centers, grinding, washing, painting, assembly and testing to shipping.
The trigger is typical. Assembly needs 200 square meters more for a new variant, the hall is full, and a request for an extension of 300 square meters for EUR 480,000 is on the table.
Goals with numbers
A goal without a number cannot rank two variants. The planning brief of the pump plant holds five:
| Goal | Today | Target |
|---|---|---|
| Transport effort, loaded meters per day | 14,100 | 8,500 or less |
| Assembly area, square meters | 800 | 1,000 |
| Buffer areas, square meters | 500 | 100 |
| Reserve for growth, square meters | 0 | 200 |
A fifth goal limits the money: the investment has to stay below the cost of the extension.
The brief also names the planning horizon, here three years with 28,800 units per year as the upper scenario, the team, and the person who decides.
Five sets of data
- Products and quantities. Per day, for the horizon, with the future mix. A layout planned with the volume of last year is too small on the day it starts.
- Routings. The sequence of areas per product family. The system shows the plan, the floor shows the detours. Take one order per family and follow it through the hall with the plan in hand.
- Load units. Pieces per pallet or bin. Quantities become transports only through the load unit, and the layout feels transports, not pieces.
- Areas and resources. Machines with measured footprints. Old plans are rarely current.
- Fixed points. Everything the building dictates.
The pump plant makes all 18 pump variants from three part families:
| Family | Load unit | Routing | Loads per day |
|---|---|---|---|
| Housings | 4 on a pallet | Receiving, machining centers, washing, painting, assembly | 25 |
| Shafts | 10 in a bin | Receiving, sawing, turning, grinding, washing, assembly | 10 |
| Covers | 25 in a bin | Receiving, sawing, turning, machining centers, washing, assembly | 8 |
Housings: 100 per day divided by 4 per pallet gives 25 pallets per day on every leg of the routing.
Fixed points and monuments
A fixed point is given by the building: docks, columns, pits, floor loads, drains, exhaust. A monument is a resource that could move, but only at a cost nobody wants to pay.
List both, and put a price on every monument. The paint shop of the pump plant would cost EUR 420,000 to move, with three weeks without painting. That makes it a monument. The receiving dock in the northwest and the shipping dock in the southwest are fixed points. Most other things called immovable cost a few thousand euros.
One plan as the basis
Everything that follows is calculated on one plan, so it has to be right. Measure the hall instead of copying the old drawing, and put a planning grid on it that fits the column grid. The pump plant uses cells of 10 m by 10 m, which gives 48 cells of 100 square meters. Every square meter belongs to an area, including the corners where pallets wait.
With goals, data and one accepted plan, the next step can be done with arithmetic instead of opinion: counting what flows between the areas.