An external certification is a project with a sponsor, a plan and a budget. It is prepared by building a system that works, not by rehearsing answers for the auditor. The plant in this series had twelve months until its recertification audit, and a last audit with 2 major and 9 minor findings behind it.
Seven phases
Decide. Which standard, which scope, why, by when. Obtain the valid edition of the standard.
Compare. Read the standard with the process owners and note where each requirement is met in your system. The result is a gap list.
Build. Close the gaps inside the processes: purpose and scope, objectives, landscape and profiles, documents, roles, control points, providers, the action register. The system should be in use for at least three months before the audit.
Check yourself. Internal audits of all processes, a management review, a readiness score.
Pre-assessment. Optional: one or two days with an external auditor, before it counts.
Certification audit. Usually in two steps: a look at readiness and documents, then the audit of practice in all processes.
Afterward. Close the findings in the agreed time. Surveillance audits follow, usually yearly.
The reference table
Auditors need to find where each requirement is met. Many plants therefore rebuild their manual in the order of the standard, and end up with a document that describes the standard instead of the plant.
There is a better way. Keep your own structure and add one table: on the left the section of the standard, on the right the process, profile or document of your system that answers it. You fill it from your own copy of the standard.
Readiness per element
The plant scored twelve elements of its system on five levels: 0 not in place, 1 on paper, 2 in use in parts, 3 in use everywhere and measured, 4 improved with its own data.
| Element | Start | Month 12 |
|---|---|---|
| Process landscape and owners | 1 | 4 |
| Documents and records | 1 | 3 |
| External providers | 2 | 3 |
| Nonconformity and corrective action | 1 | 3 |
| Management review | 1 | 3 |
| Average of all twelve elements | 1.3 | 3.1 |
The plant asked for the audit only when no element was below level 3.
Findings that come up often
Five findings appear in audit reports again and again. Objectives without numbers, dates or owners. Processes that are described, but with no evidence that they are measured. Corrective actions closed without a check of the effect. Outsourced processes without defined control. Training lists without evidence of ability.
What happened
The pre-assessment in month 10 found 1 major and 6 minor points. The major one was the missing control of an outsourced coating process. The recertification audit in month 12 ended with 0 major and 3 minor findings.
Effort and benefit
The effort was counted honestly.
| Item | EUR |
|---|---|
| Internal effort, 1,840 hours at EUR 60 | 110,400 |
| Training for process owners and auditors | 8,200 |
| Pre-assessment and recertification audit | 11,400 |
| Total effort | 130,000 |
The benefit per year has three parts. Scrap and rework fell from 3.1 to 2.6 percent of EUR 46 million sales: EUR 230,000. Complaints fell from 58 to 31, at EUR 4,000 each: EUR 108,000. And 226 documents fewer save EUR 20,340 in upkeep. Together that is EUR 358,340, and a payback of 4.4 months. Other projects contributed. The plant attributes the gain to the system because the actions ran through the profiles and the register.
What stays after the audit
The certificate is a by-product. What stays is a rhythm: overdue actions every week, key figures and the quality meeting every month, the management review twice a year, and once a year a review of every profile and the score with 25 statements, which rose from 41 to 72 points.