A management system produces a lot of data. The art is to look at little of it, at a fixed time, and to write down what follows. Twice a year, top management then looks at the whole and decides. That meeting is the management review, and in many plants it is the weakest part of the system.
What is watched
The example plant, a die caster with 260 employees, watches six things, each with a source, a person and a rhythm.
The six objectives of the plant are reviewed by all process owners in the monthly quality meeting. The 28 process key figures, two per process, are reviewed by each owner with the team, also monthly. Product conformity, from release records and scrap data, is watched by production daily and weekly. The customer view comes from complaints, scorecards and a yearly satisfaction survey. Providers are followed through receipt data and a yearly evaluation. And the system itself is watched through internal audits, overdue document reviews and overdue actions.
The monthly quality meeting
Sixty minutes, all fourteen owners, one page. Ten minutes for the six objectives. Thirty minutes for the processes that missed a target: the owner says why and what follows. Ten minutes for overdue actions. Ten minutes for decisions.
The objectives over twelve months
| Objective | Start | Month 6 | Month 12 | Target |
|---|---|---|---|---|
| Scrap and rework, percent of sales | 3.1 | 2.6 | 2.1 | 2.6 |
| On-time delivery, percent | 88 | 94 | 98 | 95 |
| Actions closed on time, percent | 55 | 73 | 85 | 85 |
| Critical roles with deputy, percent | 62 | 77 | 92 | 90 |
These are monthly values. Over the whole year, scrap and rework averaged 2.6 percent and on-time delivery 94 percent. So the delivery objective was missed by one point, although the last months were above target. An honest system reports the year, not the best month.
Before and after
The old management review took place once a year, in the week before the external audit. The quality manager prepared 46 slides. The meeting lasted three hours and produced 2 decisions without an owner.
The new review takes place twice a year. It has 12 inputs on 6 pages, each from the person who answers for it, sent one week ahead. It lasts two hours and produced 9 decisions with owner, date and resources.
Twelve inputs
The plant’s own agenda has twelve points: the decisions of the last review, what changed around the plant and inside, the six objectives, the misses among the process key figures, the customer view, nonconformities and corrective actions, audit results, external providers, resources, risks and opportunities, the state of the system, and proposals for the next period.
What a review must decide
A review without decisions is a presentation. The review in month 10 decided five kinds of things.
An improvement: a second leak test bench on one assembly line, so that on-time delivery reaches 95 percent, with a budget of EUR 38,000.
Resources: deputies for two critical roles, EUR 6,500.
Objectives for the next period: 24 complaints, 2.2 percent scrap and rework.
Changes to the system: work instructions move to a review every two years, and the process owners become key users in the ERP project.
A risk: the open clause with the coating provider gets a deadline of eight weeks.
In total EUR 44,500 were decided in the meeting. Each decision is one row in the action register.
How to run it
Send the pages one week ahead. The meeting is for questions and decisions, not for reading. Start with the decisions of the last review: unfinished ones are decided again or dropped openly. Go through the inputs by exception. Write each decision during the meeting and read it back before the next topic. End with one sentence: is the system suitable and effective, and what is the proof?