Quality Management System | Part 8 of 12

Operational Control From Order to Delivery

Seven control points along the order, the rules for changes, identification and release, and who may decide.

Operational control sounds abstract. In practice it means one thing: at defined points along the order, somebody checks against a criterion and decides whether the order may go on.

The example plant of this series casts, machines and assembles aluminum housings. When the management team followed one order through the plant, it found seven such points.

Seven control points

Control point Criterion Who releases
Order review Requirements complete, drawing revision current, feasible, date inside the lead-time table Inside sales, engineer for new parts
Production order Material, die, program and capacity available Planner
Material release Incoming material accepted, batch identified Incoming inspection
First-part release First part after every start, die change or repair meets the criteria Setter and shift lead
In-process checks Characteristics of the control plan within limits Operator
Final release Final inspection passed, quantity and label correct Final inspector
Shipping release Right part, quantity, papers, packaging, customer label Shipping clerk

The finding of the exercise was not a missing point. It was that three of the seven had no named person with the authority to release: the order review, the first-part release on the late shift and the shipping release. Everybody did it, so nobody answered for it. At the start, only 71 percent of first-part releases were recorded. After twelve months it is 99 percent.

Plan before you produce

Before a part runs, four questions are answered. What is required: drawing, specification, customer-specific and legal requirements for the product. How it will be made: routing, work instructions, capable equipment, qualified people. How conformity is shown: which checks, by whom, with which measuring equipment, recorded where. And what happens when it fails: who stops, who decides, where blocked product goes.

Changes

A controlled process stays controlled only if nothing changes without a decision. The plant distinguishes four kinds of change.

A planned change of product or process, such as a new drawing revision or a new die, needs a change request with evaluation and decision before the change. The series on engineering change covers this path.

A change of a document is decided by the process owner and leads to a new version and, where needed, training.

A change of the system itself, such as a new process owner or the new ERP, is decided by top management with a look at what else it touches: people, documents, figures.

A temporary deviation, such as an alternative material for one batch, needs written permission for a quantity or a period, from the customer where required.

Identification and status

At any time, every part in the plant shows what it is and what may be done with it. The plant uses four states.

Released parts carry a green tag or a booked status in the system and stay in the normal flow. Parts on hold get a yellow tag with reason, date and name. Any employee may set it, and it lasts at most 24 hours. Blocked parts get a red tag with a report number, set by the shift lead or quality, and move to a locked area. Scrap goes into red containers and is counted.

Release authority

Release authority is given by name, in writing, after the ability was shown. The plant keeps one list with 11 release authorities for first parts, final inspection, shipping and concessions. It is part of the list of critical roles, and it is reviewed when a person changes the area.

What it changed

Control points are not new checks. Most of them existed. What changed is that each one now has a criterion, a name and a record. The effect shows in the figures of the plant: scrap and rework fell from 3.1 to 2.6 percent of sales, and the share of orders confirmed with a feasibility check rose from 64 to 98 percent.