Risk thinking in a management system has a simple core. For every process, ask two questions: what could keep it from delivering its result, and what could make it better than planned? Then act on the few answers that matter.
Where risks are found
There are four sources, and none of them needs a workshop of its own.
The process profile asks what goes wrong most often or hurts most. In the process that accepts orders, the answer was: an order is confirmed against an outdated drawing revision.
The page on expectations and changes shows what is coming. Three senior setters retire within two years.
Audit findings, complaints and nonconformities show what already happened. Corrective actions were closed without a check of the effect.
Handovers and external providers hide risks that belong to nobody. The coating provider can change its process without telling the plant.
A simple rating
The plant rates likelihood from 1 to 3 (rare, possible, frequent) and impact from 1 to 3 (a nuisance, the customer notices, the customer is harmed or supply stops). The score is the product. A score of 6 or 9 is high and needs an action with owner and date. A score of 3 or 4 is watched. Below that, nothing is done.
The five high risks
The list holds 24 entries: 18 risks and 6 opportunities. Five risks were rated high at the start.
| Risk | Process | Action | Score before | Score after |
|---|---|---|---|---|
| Order confirmed against an outdated drawing revision | Orders | Revision check at order entry | 6 | 3 |
| Delivery date confirmed without capacity check | Orders | Lead-time table from planning | 6 | 2 |
| Series production starts before customer approval | Launch | Release gate in the launch plan | 6 | 3 |
| Outsourced coating process changes without notice | Purchasing | Change notification in the supply agreement | 6 | 6 |
| Only two setters can change dies on two cells | Production | Two more setters qualified | 9 | 3 |
Four of the five came down. One did not: the agreement with the coating provider is not signed yet, so the score stays at 6. The management review has set a deadline of eight weeks and named the alternative, which is to approve a second provider. That is how a risk list should work. It does not hide what is still open.
Opportunities
Opportunities are the neglected half. The plant found six. The most useful one came from the same process as two of the high risks: a standard lead-time table from planning lets sales confirm dates within one day instead of asking the planner for every order. It reduced a risk and shortened the quotation lead time from 9 to 5 working days.
Three rules
Keep risks in the profile. The owner reviews them with the key figures, once a year and after every larger change. A risk that came true is a nonconformity and goes into the action register.
Act on the high ones only. Eighteen risks with eighteen action plans end as eighteen unfinished plans. Five actions with owners and dates get done.
Rate again after the action. The second rating is the check of whether the action worked. If the score has not moved, the action was not the right one or is not finished.
What this is not
This is the level of risk thinking a management system needs. It is not a full risk management for a plant, and it is not the analysis of product and process failures. Those have their own methods and their own series: operational risk management for the plant, and FMEA with the control plan for products and processes. The management system only makes sure that each process owner knows the few things that could stop the process, and has done something about them.